Mitigation of Time Overruns in Construction Projects in Afghanistan by Applying Risk Management

Construction industry in Afghanistan is crucial for economic and social advancement, particularly after years of instability. However, the construction industry has been already confronting huge time overruns, affecting all stakeholders. This research aims to identify the various risks associated with time overruns in construction projects within Afghanistan and to explore effective risk management strategies to mitigate these challenges. To address time overruns, this study employed Monte Carlo simulations using RiskPert to assess time overruns by combining expert judgment with historical data. This study assesses construction project historical data from 2002 to 2023, emphasizing the political and economic circumstances of that period using a literature review and an examination of 74 construction project reports, in addition to semi-structured interviews with industry experts to determine schedule-related risks and their frequent causes. This research found 29 distinct risk indicators classified into eight categories, facilitating a methodical integration of risks into the simulation model. The Monte Carlo Simulations conducted with @RISK software (version 8.0, Palisade Corporation, New York, NY, USA) assessed the influence of these risks on project performance over 10,000 iterations, demonstrating a robust association with actual project results and a standard deviation of ±15% in durations. Time overruns in projects are linked to socio-political, organizational, and financial risks. The findings emphasize the significance of these factors on project outcomes and recommend strategies for their mitigation to improve decision-making and ensure project management success.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2026-01-25
DOI
https://doi.org/10.3390/buildings16030491
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Mitigation of Time Overruns in Construction Projects in Afghanistan by Applying Risk Management

Tahir Çelik, Inayatullah Mohib Inayatullah Mohib
Buildings
Construction Project Management and Performance
article

Mitigation of Time Overruns in Construction Projects in Afghanistan by Applying Risk Management

Tahir Çelik, Inayatullah Mohib Inayatullah Mohib
article en

Abstract

Construction industry in Afghanistan is crucial for economic and social advancement, particularly after years of instability. However, the construction industry has been already confronting huge time overruns, affecting all stakeholders. This research aims to identify the various risks associated with time overruns in construction projects within Afghanistan and to explore effective risk management strategies to mitigate these challenges. To address time overruns, this study employed Monte Carlo simulations using RiskPert to assess time overruns by combining expert judgment with historical data. This study assesses construction project historical data from 2002 to 2023, emphasizing the political and economic circumstances of that period using a literature review and an examination of 74 construction project reports, in addition to semi-structured interviews with industry experts to determine schedule-related risks and their frequent causes. This research found 29 distinct risk indicators classified into eight categories, facilitating a methodical integration of risks into the simulation model. The Monte Carlo Simulations conducted with @RISK software (version 8.0, Palisade Corporation, New York, NY, USA) assessed the influence of these risks on project performance over 10,000 iterations, demonstrating a robust association with actual project results and a standard deviation of ±15% in durations. Time overruns in projects are linked to socio-political, organizational, and financial risks. The findings emphasize the significance of these factors on project outcomes and recommend strategies for their mitigation to improve decision-making and ensure project management success.

BuildingsVol. 16(3)
Cyprus International University (CY)
Openalex Percentile: Top 80%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Mitigation of Time Overruns in Construction Projects in Afghanistan by Applying Risk Management — Tahir Çelik, Inayatullah Mohib Inayatullah Mohib · Buildings (2026) | TGRS Research Map | TGRS