Commissioning and First Operation of SLS 2.0, the Upgrade of the Swiss Light Source

After more than 20 years of successful operation, the storage ring of the Swiss Light Source (SLS) has recently been replaced with a new diffraction-limited storage ring (DLSR) called SLS 2.0. After a dark time of 15 months from October 2023 until December 2024, SLS 2.0 now provides more than 40 times higher brilliance for hard X-ray users, thanks to an innovative compact 7-bend achromat magnet lattice with reverse bending magnets that fits into the old SLS 1.0 tunnel. In this contribution, we give an overview of the commissioning of the new storage ring and first user operation experience, highlighting key differences between SLS 1.0 and 2.0, as well as the role and usage of different beam instrumentation systems during the commissioning process from the operations perspective. Moreover, we present the status of beam-based feedbacks systems, and the resulting beam stability and performance that has been achieve so far during first user operation.

Authors

Publication Details

Journal
JACOW
Published
2026-01-20
DOI
https://doi.org/10.18429/jacow-ibic2025-moci01
Primary Topic
Particle Accelerators and Free-Electron Lasers
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Commissioning and First Operation of SLS 2.0, the Upgrade of the Swiss Light Source

B. Keil
JACOW
Particle Accelerators and Free-Electron Lasers
article

Commissioning and First Operation of SLS 2.0, the Upgrade of the Swiss Light Source

B. Keil
article en

Abstract

After more than 20 years of successful operation, the storage ring of the Swiss Light Source (SLS) has recently been replaced with a new diffraction-limited storage ring (DLSR) called SLS 2.0. After a dark time of 15 months from October 2023 until December 2024, SLS 2.0 now provides more than 40 times higher brilliance for hard X-ray users, thanks to an innovative compact 7-bend achromat magnet lattice with reverse bending magnets that fits into the old SLS 1.0 tunnel. In this contribution, we give an overview of the commissioning of the new storage ring and first user operation experience, highlighting key differences between SLS 1.0 and 2.0, as well as the role and usage of different beam instrumentation systems during the commissioning process from the operations perspective. Moreover, we present the status of beam-based feedbacks systems, and the resulting beam stability and performance that has been achieve so far during first user operation.

JACOW
Openalex Percentile: Top 83%
Particle Accelerators and Free-Electron Lasers
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.