Strategic Insights from Equipment Rental Negotiations in Brazilian Construction Projects

This article examines a real-world negotiation for the rental of a hydraulic excavator in a construction project in Campinas/SP. The situation shows how budget constraints, strict payment terms, short project timelines, and low supplier inventory levels make negotiations more challenging. The negotiation began as a dispute over the position between the company's budget limit and the supplier's high proposal, but both sides eventually revealed their core requirements, leading to an integrated solution. The parties established their Zone of Possible Agreement (ZOPA) as ranging from R$45,000 to R$50,000 through their evaluation of three creative solutions that eliminated moving costs, added protective measures, and created potential future commercial partnerships. The final contract agreement for R$47,000 fulfilled all requirements while demonstrating that procurement success depends on maintaining open communication and showing respect to all parties involved in the negotiation process. The case demonstrates how evaluating BATNA and using interest-based negotiation techniques enable teams to transform opposing positions into collaborative solutions that construction managers and supply chain specialists can apply.

Authors

Institutions

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2026-01-16
DOI
https://doi.org/10.5281/zenodo.18267798
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Strategic Insights from Equipment Rental Negotiations in Brazilian Construction Projects

Diego Priscila Olinda da Silva Martins, Murillo de Oliveira Dias
Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
article

Strategic Insights from Equipment Rental Negotiations in Brazilian Construction Projects

Diego Priscila Olinda da Silva Martins, Murillo de Oliveira Dias
article en

Abstract

This article examines a real-world negotiation for the rental of a hydraulic excavator in a construction project in Campinas/SP. The situation shows how budget constraints, strict payment terms, short project timelines, and low supplier inventory levels make negotiations more challenging. The negotiation began as a dispute over the position between the company's budget limit and the supplier's high proposal, but both sides eventually revealed their core requirements, leading to an integrated solution. The parties established their Zone of Possible Agreement (ZOPA) as ranging from R$45,000 to R$50,000 through their evaluation of three creative solutions that eliminated moving costs, added protective measures, and created potential future commercial partnerships. The final contract agreement for R$47,000 fulfilled all requirements while demonstrating that procurement success depends on maintaining open communication and showing respect to all parties involved in the negotiation process. The case demonstrates how evaluating BATNA and using interest-based negotiation techniques enable teams to transform opposing positions into collaborative solutions that construction managers and supply chain specialists can apply.

Zenodo (CERN European Organization for Nuclear Research)
Fundação Getulio Vargas (BR)
Partnerships for the goals
Openalex Percentile: Top 88%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Strategic Insights from Equipment Rental Negotiations in Brazilian Construction Projects — Diego Priscila Olinda da Silva Martins, Murillo de Oliveira Dias · Zenodo (CERN European Organization for Nuclear Research) (2026) | TGRS Research Map | TGRS