Potential of Different Machine Learning Methods in Cost Estimation of High-Rise Construction in Croatia

The fundamental goal of a construction project is to complete the construction phase within budget, but in practice, planned cost estimates are often exceeded. The causes of overruns can be due to insufficient preparation and planning of the project, changes during construction, activation of risky events, etc. Also, construction costs are often calculated based on experience rather than scientifically based approaches. Due to the challenges, this paper investigates the potential of several different machine learning methods (linear regression, decision tree forest, support vector machine and general regression neural network) for estimating construction costs. The methods were implemented on a database of recent high-rise construction projects in the Republic of Croatia. Results confirmed the potential of the selected assessment methods; in particular, the support vector machine stands out in terms of accuracy metrics. Established machine learning models contribute to a deeper understanding of real construction costs, their optimization, and more effective cost management during the construction phase.

Authors

Institutions

Publication Details

Journal
Information
Published
2026-01-15
DOI
https://doi.org/10.3390/info17010091
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Potential of Different Machine Learning Methods in Cost Estimation of High-Rise Construction in Croatia

Ksenija Tijanić Štrok
Information
Construction Project Management and Performance
article

Potential of Different Machine Learning Methods in Cost Estimation of High-Rise Construction in Croatia

Ksenija Tijanić Štrok
article en

Abstract

The fundamental goal of a construction project is to complete the construction phase within budget, but in practice, planned cost estimates are often exceeded. The causes of overruns can be due to insufficient preparation and planning of the project, changes during construction, activation of risky events, etc. Also, construction costs are often calculated based on experience rather than scientifically based approaches. Due to the challenges, this paper investigates the potential of several different machine learning methods (linear regression, decision tree forest, support vector machine and general regression neural network) for estimating construction costs. The methods were implemented on a database of recent high-rise construction projects in the Republic of Croatia. Results confirmed the potential of the selected assessment methods; in particular, the support vector machine stands out in terms of accuracy metrics. Established machine learning models contribute to a deeper understanding of real construction costs, their optimization, and more effective cost management during the construction phase.

InformationVol. 17(1)
University of Rijeka (HR)
Openalex Percentile: Top 88%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Potential of Different Machine Learning Methods in Cost Estimation of High-Rise Construction in Croatia — Ksenija Tijanić Štrok · Information (2026) | TGRS Research Map | TGRS