Stakeholder perceptions of delay causes in Orthodox church construction projects

Purpose Construction project delays are a widespread issue globally. This study aimed to identify significant delay factors in church construction projects unanimously agreed upon by all stakeholders. Design/methodology/approach A structured questionnaire incorporating Likert-scale items was used to collect data from experts and volunteers directly involved in the design, supervision and construction of Orthodox church projects. The respondents included professionals with backgrounds in architecture, civil engineering, construction management and related fields as well as key volunteers familiar with the operational aspects of church construction. The study employed multiple statistical techniques to analyze the data. These included tests for normality, reliability analysis (where a Cronbach’s alpha of 0.66 was deemed acceptable for exploratory research based on Noble et al., 2021), Spearman’s rank correlation to identify relationships between delay factors, Mann–Whitney U tests to assess differences in perception among stakeholder groups, and the Relative Importance Index (RII) to rank the significance of the identified delay factors. Findings The study identified several significant delay factors unanimously recognized by all stakeholders, including the complexity of the structures, a shortage of skilled professionals within the construction committee, delayed delivery of materials and equipment and ineffective project planning and scheduling. Practical implications The identification of these delay factors provides valuable insights for project managers and stakeholders to address and mitigate delays in church construction projects, ultimately improving project efficiency and success. Originality/value This study contributes to the understanding of delay factors in church construction projects and offers practical recommendations for enhancing project management practices in the construction industry.

Authors

Institutions

Publication Details

Journal
Engineering Construction & Architectural Management
Published
2026-01-07
DOI
https://doi.org/10.1108/ecam-06-2024-0697
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Stakeholder perceptions of delay causes in Orthodox church construction projects

Teshale Teshome Alemu, Mohindra Singh Thakur
Engineering Construction & Architectural Management
Construction Project Management and Performance
article

Stakeholder perceptions of delay causes in Orthodox church construction projects

Teshale Teshome Alemu, Mohindra Singh Thakur
article en

Abstract

Purpose Construction project delays are a widespread issue globally. This study aimed to identify significant delay factors in church construction projects unanimously agreed upon by all stakeholders. Design/methodology/approach A structured questionnaire incorporating Likert-scale items was used to collect data from experts and volunteers directly involved in the design, supervision and construction of Orthodox church projects. The respondents included professionals with backgrounds in architecture, civil engineering, construction management and related fields as well as key volunteers familiar with the operational aspects of church construction. The study employed multiple statistical techniques to analyze the data. These included tests for normality, reliability analysis (where a Cronbach’s alpha of 0.66 was deemed acceptable for exploratory research based on Noble et al., 2021), Spearman’s rank correlation to identify relationships between delay factors, Mann–Whitney U tests to assess differences in perception among stakeholder groups, and the Relative Importance Index (RII) to rank the significance of the identified delay factors. Findings The study identified several significant delay factors unanimously recognized by all stakeholders, including the complexity of the structures, a shortage of skilled professionals within the construction committee, delayed delivery of materials and equipment and ineffective project planning and scheduling. Practical implications The identification of these delay factors provides valuable insights for project managers and stakeholders to address and mitigate delays in church construction projects, ultimately improving project efficiency and success. Originality/value This study contributes to the understanding of delay factors in church construction projects and offers practical recommendations for enhancing project management practices in the construction industry.

Engineering Construction & Architectural Management
Shoolini University (IN)
Openalex Percentile: Top 95%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Stakeholder perceptions of delay causes in Orthodox church construction projects — Teshale Teshome Alemu, Mohindra Singh Thakur · Engineering Construction & Architectural Management (2026) | TGRS Research Map | TGRS