Factors affecting delays in oil and gas construction projects

Ensuring the timely completion of construction projects is vital for overall efficiency. This study aims to identify, classify, and rank the main factors of delay in Egyptian oil and gas construction projects related to project stakeholders. A mixed-methods approach was used to Sharkia collect and analyze both quantitative and qualitative data. Data was gathered from 71 sector respondents. Expert interviews refined the delay factors from the literature to 20 for contractors, 17 for owners, and 13 related to consultants. Financial difficulties, late payments to suppliers and subcontractors, and supplier material delivery delays were the significant causes related to the contractor. Delays associated with owners came from ineffective contractor selection and government regulations. Consultants contributed to delays in finalizing drawings and designs. To provide a deeper understanding of the interrelationships among these factors and their collective effect on project delay, a structural model was developed and evaluated. The structural model demonstrated that deficiencies in project planning, design management, and owner decision-making collectively contribute to delays. This provides a basis for developing integrated management approaches to mitigate future delays and improve project performance in Egypt's oil and gas construction sector.

Authors

Institutions

Publication Details

Journal
Scientific Reports
Published
2025-12-27
DOI
https://doi.org/10.1038/s41598-025-31645-3
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Factors affecting delays in oil and gas construction projects

Medhat Youssef, Omar A. Hagras, Ahmed Gab-Allah, Ibrahim Bahader
Scientific Reports
Construction Project Management and Performance
article

Factors affecting delays in oil and gas construction projects

Medhat Youssef, Omar A. Hagras, Ahmed Gab-Allah, Ibrahim Bahader
article en

Abstract

Ensuring the timely completion of construction projects is vital for overall efficiency. This study aims to identify, classify, and rank the main factors of delay in Egyptian oil and gas construction projects related to project stakeholders. A mixed-methods approach was used to Sharkia collect and analyze both quantitative and qualitative data. Data was gathered from 71 sector respondents. Expert interviews refined the delay factors from the literature to 20 for contractors, 17 for owners, and 13 related to consultants. Financial difficulties, late payments to suppliers and subcontractors, and supplier material delivery delays were the significant causes related to the contractor. Delays associated with owners came from ineffective contractor selection and government regulations. Consultants contributed to delays in finalizing drawings and designs. To provide a deeper understanding of the interrelationships among these factors and their collective effect on project delay, a structural model was developed and evaluated. The structural model demonstrated that deficiencies in project planning, design management, and owner decision-making collectively contribute to delays. This provides a basis for developing integrated management approaches to mitigate future delays and improve project performance in Egypt's oil and gas construction sector.

Scientific ReportsVol. 15(1)
Zagazig University (EG)
Zagazig University
Openalex Percentile: Top 28%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.