Intelligent Workforce Scheduling in Manufacturing: An Integrated Optimization Framework Using Genetic Algorithm, Monte Carlo Simulation, and Taguchi Method

Small and medium-sized enterprises (SMEs) constitute a substantial share of industrial production. However, their operational performance is frequently constrained by delivery delays caused by inefficiencies in workforce scheduling and task sequencing. These limitations reduce overall competitiveness, particularly in project-based manufacturing environments where task heterogeneity and multi-skill variability are prominent. To address this challenge, this study develops an artificial intelligence based workforce planning framework tailored to capital-constrained manufacturing settings. The new proposed hybrid system integrates a Genetic Algorithm (GA), Monte Carlo Simulation (MCS), and Taguchi methodology to generate robust, uncertainty-aware labor assignments. The framework is validated through 18-month deployments in two manufacturing facilities with differing levels of technological maturity, demonstrating consistent improvements in operational outcomes. Furthermore, specific weekly examples were validated against the solutions of exact mixed integer linear programming solvers on the deterministic core to assess the optimality gap and ensure constant solution quality. Across the deployments, the system achieved 13% and 15% reduction in task completion times. The resulting GA–MCS–Taguchi pipeline operates efficiently on standard SMEs hardware, requires only short historical performance windows for calibration, and exhibits high user adoption in real industrial settings, which indicates strong operational viability and practical deployability.

Authors

Institutions

Publication Details

Journal
Systems
Published
2025-12-25
DOI
https://doi.org/10.3390/systems14010026
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Intelligent Workforce Scheduling in Manufacturing: An Integrated Optimization Framework Using Genetic Algorithm, Monte Carlo Simulation, and Taguchi Method

Berrin Denizhan, Bengisu Derya, Elif Yıldırım, Mehmet Efe Erbaş et al.
Systems
Resource-Constrained Project Scheduling
article

Intelligent Workforce Scheduling in Manufacturing: An Integrated Optimization Framework Using Genetic Algorithm, Monte Carlo Simulation, and Taguchi Method

Berrin Denizhan, Bengisu Derya, Elif Yıldırım, Mehmet Efe Erbaş, Batuhan Öz, Beyza Fındıklı
article en

Abstract

Small and medium-sized enterprises (SMEs) constitute a substantial share of industrial production. However, their operational performance is frequently constrained by delivery delays caused by inefficiencies in workforce scheduling and task sequencing. These limitations reduce overall competitiveness, particularly in project-based manufacturing environments where task heterogeneity and multi-skill variability are prominent. To address this challenge, this study develops an artificial intelligence based workforce planning framework tailored to capital-constrained manufacturing settings. The new proposed hybrid system integrates a Genetic Algorithm (GA), Monte Carlo Simulation (MCS), and Taguchi methodology to generate robust, uncertainty-aware labor assignments. The framework is validated through 18-month deployments in two manufacturing facilities with differing levels of technological maturity, demonstrating consistent improvements in operational outcomes. Furthermore, specific weekly examples were validated against the solutions of exact mixed integer linear programming solvers on the deterministic core to assess the optimality gap and ensure constant solution quality. Across the deployments, the system achieved 13% and 15% reduction in task completion times. The resulting GA–MCS–Taguchi pipeline operates efficiently on standard SMEs hardware, requires only short historical performance windows for calibration, and exhibits high user adoption in real industrial settings, which indicates strong operational viability and practical deployability.

SystemsVol. 14(1)
Sakarya University (TR)
Industry, innovation and infrastructure
Openalex Percentile: Top 28%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.