Real-time prediction of project duration deviation using CNN-LSTM-FIS

Purpose This study aims to develop a real-time system for monitoring deviations in construction project durations, enabling project managers to detect schedule delays early and take proactive measures to mitigate risks. Design/methodology/approach A hybrid predictive framework combining convolutional neural networks (CNN), long short-term memory (LSTM) and a fuzzy inference systems (FIS) is proposed. The CNN models classify construction activities from daily site images, while the LSTM networks predict activity durations based on time-series data extracted from metadata and daily reports. Deviations are identified by comparing predicted and planned completion times. The FIS is used to incorporate uncertainty and interpret deviation predictions and classify deviation predictions severity in real time. Findings The model was validated using data from a water reservoir construction project in Iran. The CNN achieved 90% classification accuracy, and LSTM reported a Mean Absolute Error of 0.2. The integrated system achieved a mean absolute percentage error of 14.65% for project deviation, indicating good predictive performance. Research limitations/implications The model was evaluated on a single infrastructure project. Future studies should assess its generalizability across diverse project types, scales and conditions. Practical implications The system supports proactive construction management by integrating real-time visual and contextual data. It reduces reliance on manual progress tracking and facilitates early corrective actions to avoid cost and schedule overruns. Originality/value This framework uniquely combines sequential forecasting, image classification and fuzzy logic to address limitations of previous models and advance intelligent construction monitoring systems.

Authors

Institutions

Publication Details

Journal
Built Environment Project and Asset Management
Published
2025-12-24
DOI
https://doi.org/10.1108/bepam-01-2025-0003
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Real-time prediction of project duration deviation using CNN-LSTM-FIS

J. Gheidar-Kheljani, Mohammad Hosein Karimi Gavareshki, Fateme Malekaee Ashtiyani
Built Environment Project and Asset Management
Construction Project Management and Performance
article

Real-time prediction of project duration deviation using CNN-LSTM-FIS

J. Gheidar-Kheljani, Mohammad Hosein Karimi Gavareshki, Fateme Malekaee Ashtiyani
article en

Abstract

Purpose This study aims to develop a real-time system for monitoring deviations in construction project durations, enabling project managers to detect schedule delays early and take proactive measures to mitigate risks. Design/methodology/approach A hybrid predictive framework combining convolutional neural networks (CNN), long short-term memory (LSTM) and a fuzzy inference systems (FIS) is proposed. The CNN models classify construction activities from daily site images, while the LSTM networks predict activity durations based on time-series data extracted from metadata and daily reports. Deviations are identified by comparing predicted and planned completion times. The FIS is used to incorporate uncertainty and interpret deviation predictions and classify deviation predictions severity in real time. Findings The model was validated using data from a water reservoir construction project in Iran. The CNN achieved 90% classification accuracy, and LSTM reported a Mean Absolute Error of 0.2. The integrated system achieved a mean absolute percentage error of 14.65% for project deviation, indicating good predictive performance. Research limitations/implications The model was evaluated on a single infrastructure project. Future studies should assess its generalizability across diverse project types, scales and conditions. Practical implications The system supports proactive construction management by integrating real-time visual and contextual data. It reduces reliance on manual progress tracking and facilitates early corrective actions to avoid cost and schedule overruns. Originality/value This framework uniquely combines sequential forecasting, image classification and fuzzy logic to address limitations of previous models and advance intelligent construction monitoring systems.

Built Environment Project and Asset ManagementVol. 16(2)
Malek Ashtar University of Technology (IR)
Industry, innovation and infrastructure
Openalex Percentile: Top 29%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Real-time prediction of project duration deviation using CNN-LSTM-FIS — J. Gheidar-Kheljani, Mohammad Hosein Karimi Gavareshki, et al. · Built Environment Project and Asset Management (2025) | TGRS Research Map | TGRS