Financial and operational effects of cost estimation inaccuracy, material price volatility, and payment delays in Nigerian construction projects

Abstract This study examined the impact of poor cost estimation, material price fluctuations, and payment delays on construction project performance and financial health in Nigeria. A quantitative approach was employed, collecting data via an online survey of 74 construction professionals, including quantity surveyors and contractors. Cost estimation errors, price variations, and payment delays were analysed using a five-point Likert scale and the Relative Importance Index (RII). Findings revealed that errors in the Bill of Quantities (BOQ) significantly damage professional reputation. Contractors’ chances of securing future projects were most affected (mean = 3.42), followed by quantity surveyors obtaining new commissions (mean = 3.40). Underestimating project costs created high risks, particularly project delays and funding shortages that could result in bankruptcy (mean = 3.78). Contractors faced the greatest financial loss due to reduced profit margins from underestimation (mean = 3.88). Material cost fluctuations were another key concern, with inflation in building materials ranked highest (mean = 4.92), followed by rising transportation costs (mean = 4.76). Payment delays further contributed to cost overruns and schedule disruptions. The main causes were poor availability of client funds (RII = 0.71) and disputes over work valuation (RII = 0.72). The study underscores the importance of accurate cost estimation to safeguard company finances and maintain project schedules. It recommends improving costing methodologies, strengthening stakeholder communication, and mitigating payment delays through enhanced contract management and financial controls. These findings provide practical strategies for reducing financial and operational risks associated with cost inaccuracies and delayed payments in construction projects.

Institutions

Publication Details

Journal
Smart Construction and Sustainable Cities
Published
2025-12-14
DOI
https://doi.org/10.1007/s44268-025-00076-4
Citations
1
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
2.11

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Financial and operational effects of cost estimation inaccuracy, material price volatility, and payment delays in Nigerian construction projects

1 citations
Smart Construction and Sustainable Cities
Construction Project Management and Performance
2.11
article

Financial and operational effects of cost estimation inaccuracy, material price volatility, and payment delays in Nigerian construction projects

article en
1 citations

Abstract

Abstract This study examined the impact of poor cost estimation, material price fluctuations, and payment delays on construction project performance and financial health in Nigeria. A quantitative approach was employed, collecting data via an online survey of 74 construction professionals, including quantity surveyors and contractors. Cost estimation errors, price variations, and payment delays were analysed using a five-point Likert scale and the Relative Importance Index (RII). Findings revealed that errors in the Bill of Quantities (BOQ) significantly damage professional reputation. Contractors’ chances of securing future projects were most affected (mean = 3.42), followed by quantity surveyors obtaining new commissions (mean = 3.40). Underestimating project costs created high risks, particularly project delays and funding shortages that could result in bankruptcy (mean = 3.78). Contractors faced the greatest financial loss due to reduced profit margins from underestimation (mean = 3.88). Material cost fluctuations were another key concern, with inflation in building materials ranked highest (mean = 4.92), followed by rising transportation costs (mean = 4.76). Payment delays further contributed to cost overruns and schedule disruptions. The main causes were poor availability of client funds (RII = 0.71) and disputes over work valuation (RII = 0.72). The study underscores the importance of accurate cost estimation to safeguard company finances and maintain project schedules. It recommends improving costing methodologies, strengthening stakeholder communication, and mitigating payment delays through enhanced contract management and financial controls. These findings provide practical strategies for reducing financial and operational risks associated with cost inaccuracies and delayed payments in construction projects.

Smart Construction and Sustainable CitiesVol. 3(1)
Mbarara University of Science and Technology (UG)
Mbarara University of Science and Technology
Openalex Percentile: Top 9%
Construction Project Management and Performance
2.11
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.