U–CARE–PM: A real-time gating framework for catastrophic risk in critical utility projects

Critical utility projects cannot pause scheduled milestones without risking severe operational and regulatory disruptions. This study introduces U–CARE–PM, a six-component framework—Real-Time Continuity Gate (RTCG), Continuity–Compliance Gauge (CCG), Log-Scaled Catastrophic Risk (LSCR) index, Regulatory Feed Engine (RFE), Resource Allocation Matrix (RAM), and an optional Early Compliance Drift Indicator (ECDI)—designed to manage high-impact, low-probability (HILP) threats under continuous operations. A multi-case study was conducted across four anonymized organizations—engineering services, infrastructure construction, IoT water-tech, and a multinational energy–water operator—over a six- to twelve-month period. U–CARE–PM was integrated into existing ERP-BPMS or SCADA systems, with tiered implementations reflecting digital maturity. Data sources included operational logs, semi-structured interviews (8–15 participants per site), and Delphi panel validation thresholds (CCG = 0.85; LSCR = 10). Pilot deployments reduced downtime by 18–24%, lowered compliance breaches by 30–40%, and improved schedule adherence by eight points. One site prevented an estimated USD 1 million outage through near-real-time resource reallocation. While the ECDI occasionally generated false positives, it accelerated regulatory response and reduced overnight emergencies. Unlike static milestone-based controls, U–CARE–PM integrates real-time continuity metrics, log-based risk weighting, and continuous compliance updates. This framework offers a replicable, data-driven approach for nonstop infrastructure projects, enhancing resilience and agility in the face of catastrophic risks. Compared with existing literature on project resilience, it advances the field by shifting from retrospective control toward proactive, continuous risk-compliance management.

Publication Details

Journal
Journal of Project Management
Published
2025-12-11
DOI
https://doi.org/10.5267/j.jpm.2025.9.001
Citations
1
Primary Topic
Infrastructure Resilience and Vulnerability Analysis
Type
article
Field-Weighted Citation Impact
0.95
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

U–CARE–PM: A real-time gating framework for catastrophic risk in critical utility projects

1 citations
Journal of Project Management
Infrastructure Resilience and Vulnerability Analysis
0.95
article

U–CARE–PM: A real-time gating framework for catastrophic risk in critical utility projects

article en
1 citations

Abstract

Critical utility projects cannot pause scheduled milestones without risking severe operational and regulatory disruptions. This study introduces U–CARE–PM, a six-component framework—Real-Time Continuity Gate (RTCG), Continuity–Compliance Gauge (CCG), Log-Scaled Catastrophic Risk (LSCR) index, Regulatory Feed Engine (RFE), Resource Allocation Matrix (RAM), and an optional Early Compliance Drift Indicator (ECDI)—designed to manage high-impact, low-probability (HILP) threats under continuous operations. A multi-case study was conducted across four anonymized organizations—engineering services, infrastructure construction, IoT water-tech, and a multinational energy–water operator—over a six- to twelve-month period. U–CARE–PM was integrated into existing ERP-BPMS or SCADA systems, with tiered implementations reflecting digital maturity. Data sources included operational logs, semi-structured interviews (8–15 participants per site), and Delphi panel validation thresholds (CCG = 0.85; LSCR = 10). Pilot deployments reduced downtime by 18–24%, lowered compliance breaches by 30–40%, and improved schedule adherence by eight points. One site prevented an estimated USD 1 million outage through near-real-time resource reallocation. While the ECDI occasionally generated false positives, it accelerated regulatory response and reduced overnight emergencies. Unlike static milestone-based controls, U–CARE–PM integrates real-time continuity metrics, log-based risk weighting, and continuous compliance updates. This framework offers a replicable, data-driven approach for nonstop infrastructure projects, enhancing resilience and agility in the face of catastrophic risks. Compared with existing literature on project resilience, it advances the field by shifting from retrospective control toward proactive, continuous risk-compliance management.

Journal of Project ManagementVol. 11(1)
Industry, innovation and infrastructure
Openalex Percentile: Top 18%
Infrastructure Resilience and Vulnerability Analysis
0.95
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

U–CARE–PM: A real-time gating framework for catastrophic risk in critical utility projects · Journal of Project Management (2025) | TGRS Research Map | TGRS