Delay causes of the site-clearance process for public infrastructure projects in Vietnam: Differences across roles and project sizes

Site clearance remains one of the most persistent causes of delay in Vietnam’s public infrastructure delivery, yet systematic evidence on how different stakeholders and project sizes perceive its underlying drivers is limited. This study investigates variations in stakeholder perceptions and project-scale effects on site clearance delays through an integrated analytical framework combining ranking, concordance, correlation, and variance analyses. Data were collected from key actors involved in land acquisition and clearance, including project owners, project management units, consultants, contractors, and land development centers, covering small, medium, and large public projects. Findings show that stakeholders share a general awareness of major delay causes but differ in prioritization based on institutional roles and responsibilities. Project owners, management units, and contractors emphasize coordination and staffing constraints, whereas consultants focus on technical and procedural issues, and land development centers view administrative and community challenges as routine. Across project sizes, perceptions diverge more strongly: small projects face capacity and resource shortages, large projects experience bureaucratic fragmentation and complex multi-agency coordination, and medium projects operate at a relatively balanced scale. These results indicate that project complexity increases nonlinearly with size, amplifying administrative and procedural burdens at both extremes. The study contributes by clarifying how institutional role and project scale shape perceptions of delay in Vietnam’s infrastructure sector. It underscores the need for scale-sensitive and role-specific management strategies to enhance the timeliness and effectiveness of site clearance processes.

Publication Details

Journal
Journal of Project Management
Published
2025-12-11
DOI
https://doi.org/10.5267/j.jpm.2025.12.001
Citations
1
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
2.11

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Delay causes of the site-clearance process for public infrastructure projects in Vietnam: Differences across roles and project sizes

1 citations
Journal of Project Management
Construction Project Management and Performance
2.11
article

Delay causes of the site-clearance process for public infrastructure projects in Vietnam: Differences across roles and project sizes

article en
1 citations

Abstract

Site clearance remains one of the most persistent causes of delay in Vietnam’s public infrastructure delivery, yet systematic evidence on how different stakeholders and project sizes perceive its underlying drivers is limited. This study investigates variations in stakeholder perceptions and project-scale effects on site clearance delays through an integrated analytical framework combining ranking, concordance, correlation, and variance analyses. Data were collected from key actors involved in land acquisition and clearance, including project owners, project management units, consultants, contractors, and land development centers, covering small, medium, and large public projects. Findings show that stakeholders share a general awareness of major delay causes but differ in prioritization based on institutional roles and responsibilities. Project owners, management units, and contractors emphasize coordination and staffing constraints, whereas consultants focus on technical and procedural issues, and land development centers view administrative and community challenges as routine. Across project sizes, perceptions diverge more strongly: small projects face capacity and resource shortages, large projects experience bureaucratic fragmentation and complex multi-agency coordination, and medium projects operate at a relatively balanced scale. These results indicate that project complexity increases nonlinearly with size, amplifying administrative and procedural burdens at both extremes. The study contributes by clarifying how institutional role and project scale shape perceptions of delay in Vietnam’s infrastructure sector. It underscores the need for scale-sensitive and role-specific management strategies to enhance the timeliness and effectiveness of site clearance processes.

Journal of Project ManagementVol. 11(1)
Ho Chi Minh City University of Technology and Education, Viet Nam National University Ho Chi Minh City
Industry, innovation and infrastructure
Openalex Percentile: Top 9%
Construction Project Management and Performance
2.11
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.