A probabilistic framework for assessing time-risk trade-offs in prefabricated construction projects

Prefabricated construction has emerged as a promising solution to the longstanding inefficiencies of the construction sector, offering benefits such as reduced construction time, enhanced safety, and improved environmental outcomes. Existing literature highlights significant advantages of prefabrication, including shortened schedules, cost savings, and sustainability improvements; however, it also acknowledges recurring challenges, notably schedule delays due to upstream and downstream risks. Despite the growing body of research, there remains a lack of a unified framework that systematically quantifies the time-related risks associated with varying levels of prefabrication. To address this gap, this study develops the Time–Risk Impact Comparison of Increasing Prefabrication (TRICIP) framework, offering a probabilistic approach to assess the evolving complexity and time risks in hybrid construction projects. Using case studies, including the Fenner Hall project in Australia, the research integrates Program Evaluation and Review Technique (PERT) analysis with a comprehensive risk factor matrix, quantifying how upstream, lead-time, logistical, and site-specific risks evolve with increasing prefabrication. The results reveal that while prefabrication accelerates project delivery, it substantially heightens complexity, particularly due to increased interdependencies and coordination demands. The study demonstrates that although prefabrication can reduce project timelines by up to 30 %, it concurrently amplifies project complexity by nearly threefold. By emphasizing the importance of early integrated design, robust supply chain collaboration, and digital tools like Building Information Modelling (BIM), the TRICIP framework provides practical guidance for managing prefabrication risks. This research contributes to advancing time-risk assessment methodologies and supports informed decision-making in prefabricated and hybrid construction project delivery. • Developed TRICIP framework to quantify time-risk trade-offs in prefabricated projects. • Integrated PERT analysis with risk trends to assess impacts of prefabrication levels. • Demonstrated prefabrication can cut 30 % project time but triples project complexity. • Identified critical upstream, logistics, and site risks influencing hybrid projects. • Provided strategies using BIM, supply chain integration, and risk-driven scheduling.

Institutions

Publication Details

Journal
Journal of Cleaner Production
Published
2025-11-26
DOI
https://doi.org/10.1016/j.jclepro.2025.147154
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A probabilistic framework for assessing time-risk trade-offs in prefabricated construction projects

Journal of Cleaner Production
BIM and Construction Integration
article

A probabilistic framework for assessing time-risk trade-offs in prefabricated construction projects

article en

Abstract

Prefabricated construction has emerged as a promising solution to the longstanding inefficiencies of the construction sector, offering benefits such as reduced construction time, enhanced safety, and improved environmental outcomes. Existing literature highlights significant advantages of prefabrication, including shortened schedules, cost savings, and sustainability improvements; however, it also acknowledges recurring challenges, notably schedule delays due to upstream and downstream risks. Despite the growing body of research, there remains a lack of a unified framework that systematically quantifies the time-related risks associated with varying levels of prefabrication. To address this gap, this study develops the Time–Risk Impact Comparison of Increasing Prefabrication (TRICIP) framework, offering a probabilistic approach to assess the evolving complexity and time risks in hybrid construction projects. Using case studies, including the Fenner Hall project in Australia, the research integrates Program Evaluation and Review Technique (PERT) analysis with a comprehensive risk factor matrix, quantifying how upstream, lead-time, logistical, and site-specific risks evolve with increasing prefabrication. The results reveal that while prefabrication accelerates project delivery, it substantially heightens complexity, particularly due to increased interdependencies and coordination demands. The study demonstrates that although prefabrication can reduce project timelines by up to 30 %, it concurrently amplifies project complexity by nearly threefold. By emphasizing the importance of early integrated design, robust supply chain collaboration, and digital tools like Building Information Modelling (BIM), the TRICIP framework provides practical guidance for managing prefabrication risks. This research contributes to advancing time-risk assessment methodologies and supports informed decision-making in prefabricated and hybrid construction project delivery. • Developed TRICIP framework to quantify time-risk trade-offs in prefabricated projects. • Integrated PERT analysis with risk trends to assess impacts of prefabrication levels. • Demonstrated prefabrication can cut 30 % project time but triples project complexity. • Identified critical upstream, logistics, and site risks influencing hybrid projects. • Provided strategies using BIM, supply chain integration, and risk-driven scheduling.

Journal of Cleaner ProductionVol. 536
CRC for Spatial information (AU), Caulfield Hospital (AU), Monash University (AU)
Openalex Percentile: Top 45%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.