THE ROLE OF NEGOTIATION IN REDUCING RISKS IN CONSTRUCTION PROJECTS: A BRAZILIAN CASE

The article conducts a single case study through descriptive methods to analyze how the construction project acquired its electrical kits. The construction project in Indaiatuba Brazil needed pre-assembled electrical kits through its concrete wall construction method so it required urgent procurement of these components. The procurement team dealt with an intricate negotiation situation because different suppliers provided different price points and delivery conditions and product quality levels. The negotiation process of the team encountered unexpected obstacles which endangered the project timeline. The team needed to create new solutions which would safeguard project essential requirements when managing project value exceeding millions of dollars. The research investigates negotiation methods which show how stakeholders use risk management to reach their objectives while obtaining maximum value. The procurement team remains uncertain about their outcome because they need to complete a contract that meets project needs but they face major challenges to overcome.

Institutions

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2025-11-23
DOI
https://doi.org/10.5281/zenodo.17687890
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

THE ROLE OF NEGOTIATION IN REDUCING RISKS IN CONSTRUCTION PROJECTS: A BRAZILIAN CASE

Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
article

THE ROLE OF NEGOTIATION IN REDUCING RISKS IN CONSTRUCTION PROJECTS: A BRAZILIAN CASE

article en

Abstract

The article conducts a single case study through descriptive methods to analyze how the construction project acquired its electrical kits. The construction project in Indaiatuba Brazil needed pre-assembled electrical kits through its concrete wall construction method so it required urgent procurement of these components. The procurement team dealt with an intricate negotiation situation because different suppliers provided different price points and delivery conditions and product quality levels. The negotiation process of the team encountered unexpected obstacles which endangered the project timeline. The team needed to create new solutions which would safeguard project essential requirements when managing project value exceeding millions of dollars. The research investigates negotiation methods which show how stakeholders use risk management to reach their objectives while obtaining maximum value. The procurement team remains uncertain about their outcome because they need to complete a contract that meets project needs but they face major challenges to overcome.

Zenodo (CERN European Organization for Nuclear Research)
Fundação Getulio Vargas (BR)
Industry, innovation and infrastructure
Openalex Percentile: Top 36%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.