Impact and Evaluation of Cost and Time Overruns in ConstructionProjects in India: A Review

Time and cost overruns are major challenges faced in the construction sector of India. They occur when a project takes longer than planned or exceeds the estimated budget. These overruns affect project performance, increase financial pressure, and delay project completion. The main causes include poor planning, design changes, lack of skilled labour, and delays in material supply. To study these issues, a questionnaire survey was prepared and distributed among engineers, contractors, and project managers. The collected data was analysed to find common reasons and their impact on project success. Based on the findings, suggestions were made to improve project scheduling, cost control, and communication. Proper monitoring, realistic estimation, and timely decision-making can help reduce time and cost overruns and improve the overall efficiency of construction projects in India.

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2025-11-20
DOI
https://doi.org/10.5281/zenodo.17657277
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Impact and Evaluation of Cost and Time Overruns in ConstructionProjects in India: A Review

Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
article

Impact and Evaluation of Cost and Time Overruns in ConstructionProjects in India: A Review

article en

Abstract

Time and cost overruns are major challenges faced in the construction sector of India. They occur when a project takes longer than planned or exceeds the estimated budget. These overruns affect project performance, increase financial pressure, and delay project completion. The main causes include poor planning, design changes, lack of skilled labour, and delays in material supply. To study these issues, a questionnaire survey was prepared and distributed among engineers, contractors, and project managers. The collected data was analysed to find common reasons and their impact on project success. Based on the findings, suggestions were made to improve project scheduling, cost control, and communication. Proper monitoring, realistic estimation, and timely decision-making can help reduce time and cost overruns and improve the overall efficiency of construction projects in India.

Zenodo (CERN European Organization for Nuclear Research)
Openalex Percentile: Top 36%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.