Commissioning of the SLS 2.0 machine protection system

The Swiss Light Source (SLS) at the Paul Scherrer Institute (PSI) was Switzerland’s first and only 3rd-generation light source. For the SLS 2.0* upgrade the old 2.4 GeV, 12-fold 3-bend achromat lattice with 5 nm horizontal emittance was decommissioned in September 2023 after 22 years of successful user operation. The new 2.7 GeV storage ring has a 12-fold 7-bend achromat lattice achieving 150 pm horizontal emittance. Injectors remain mostly unchanged: the 100 MeV linac feeds the 3 Hz booster synchrotron with extraction at 9 nm horizontal emittance and now 2.7 GeV to match the storage ring’s increased energy. Technical details and an overview of the SLS 2.0 commissioning are presented in separate contributions to this conference. This contribution focuses on the machine protection system challenges for the SLS 2.0**. These required the implementation of a sophisticated system including a fast beam dump kicker, dedicated beam dump, fast beam dump controller and a machine interlock system monitoring over 6000 signals. We discuss challenges encountered and lessons learned while commissioning this advanced machine protection system in parallel to commissioning of the new accelerator.

Publication Details

Journal
JACOW
Published
2025-11-05
DOI
https://doi.org/10.18429/jacow-ipac2025-tupm057
Primary Topic
Particle Accelerators and Free-Electron Lasers
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Commissioning of the SLS 2.0 machine protection system

JACOW
Particle Accelerators and Free-Electron Lasers
article

Commissioning of the SLS 2.0 machine protection system

article en

Abstract

The Swiss Light Source (SLS) at the Paul Scherrer Institute (PSI) was Switzerland’s first and only 3rd-generation light source. For the SLS 2.0* upgrade the old 2.4 GeV, 12-fold 3-bend achromat lattice with 5 nm horizontal emittance was decommissioned in September 2023 after 22 years of successful user operation. The new 2.7 GeV storage ring has a 12-fold 7-bend achromat lattice achieving 150 pm horizontal emittance. Injectors remain mostly unchanged: the 100 MeV linac feeds the 3 Hz booster synchrotron with extraction at 9 nm horizontal emittance and now 2.7 GeV to match the storage ring’s increased energy. Technical details and an overview of the SLS 2.0 commissioning are presented in separate contributions to this conference. This contribution focuses on the machine protection system challenges for the SLS 2.0**. These required the implementation of a sophisticated system including a fast beam dump kicker, dedicated beam dump, fast beam dump controller and a machine interlock system monitoring over 6000 signals. We discuss challenges encountered and lessons learned while commissioning this advanced machine protection system in parallel to commissioning of the new accelerator.

JACOW
Affordable and clean energy
Openalex Percentile: Top 48%
Particle Accelerators and Free-Electron Lasers
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Commissioning of the SLS 2.0 machine protection system · JACOW (2025) | TGRS Research Map | TGRS