Status of the pulsed hydrogen gas stripper project at GSI

The operation of the specifically upgraded pulsed gas stripper development setup for the user beamtime lasted until July 2024. It was very successful in terms of both providing stripped ions and gaining valuable experience in the long-term operation of the pulsed stripper. The long periods of high duty nitrogen operation revealed a severe service life issue of the fast injection valves, which was already anticipated in the risk assessment for the hydrogen operation. This emphasizes the need for the safety measures incorporated in the design of the pulsed stripper facility. During the user beamtime, several measurement campaigns were conducted. Extensive data on the stripping efficiencies for 12 projectile-target combinations could be obtained. In this contribution the obtained results and lessons learned are presentet as well as the necessary next steps to finaly bring the hydrogen stripping to routine operation.

Publication Details

Journal
JACOW
Published
2025-11-05
DOI
https://doi.org/10.18429/jacow-ipac2025-tupb034
Primary Topic
Particle accelerators and beam dynamics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Status of the pulsed hydrogen gas stripper project at GSI

JACOW
Particle accelerators and beam dynamics
article

Status of the pulsed hydrogen gas stripper project at GSI

article en

Abstract

The operation of the specifically upgraded pulsed gas stripper development setup for the user beamtime lasted until July 2024. It was very successful in terms of both providing stripped ions and gaining valuable experience in the long-term operation of the pulsed stripper. The long periods of high duty nitrogen operation revealed a severe service life issue of the fast injection valves, which was already anticipated in the risk assessment for the hydrogen operation. This emphasizes the need for the safety measures incorporated in the design of the pulsed stripper facility. During the user beamtime, several measurement campaigns were conducted. Extensive data on the stripping efficiencies for 12 projectile-target combinations could be obtained. In this contribution the obtained results and lessons learned are presentet as well as the necessary next steps to finaly bring the hydrogen stripping to routine operation.

JACOW
Responsible consumption and production
Openalex Percentile: Top 32%
Particle accelerators and beam dynamics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.