Upgrade of beam abort system at the SuperKEKB positron ring

We upgraded the beam abort system at the SuperKEKB positron ring to speed up the abort response and mitigate the damage caused by Sudden Beam Loss (SBL). An SBL event can result in the loss of tens of percent of the beam current within one or two turns. The huge radiation accompanying the beam loss can severely damage accelerator hardware and the detectors at the interaction point. The fast-response abort sensors based on the plastic scintillator and SiPM were installed to detect the beam loss from SBL earlier. Besides, the configuration of the abort trigger system (interlock) network was customized to shorten its response. The upgrade work was conducted in the 2022-2024 long shutdown and the 2024 summer shutdown. It was implemented in the beam operation in 2024. After this upgrade, we could throw abnormal beams more than one turn earlier. It is a significant treatment against SBL. We report the details of the upgrade and the improved performance achieved in the 2024 operation.

Publication Details

Journal
JACOW
Published
2025-11-05
DOI
https://doi.org/10.18429/jacow-ipac2025-thps033
Primary Topic
Muon and positron interactions and applications
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Upgrade of beam abort system at the SuperKEKB positron ring

JACOW
Muon and positron interactions and applications
article

Upgrade of beam abort system at the SuperKEKB positron ring

article en

Abstract

We upgraded the beam abort system at the SuperKEKB positron ring to speed up the abort response and mitigate the damage caused by Sudden Beam Loss (SBL). An SBL event can result in the loss of tens of percent of the beam current within one or two turns. The huge radiation accompanying the beam loss can severely damage accelerator hardware and the detectors at the interaction point. The fast-response abort sensors based on the plastic scintillator and SiPM were installed to detect the beam loss from SBL earlier. Besides, the configuration of the abort trigger system (interlock) network was customized to shorten its response. The upgrade work was conducted in the 2022-2024 long shutdown and the 2024 summer shutdown. It was implemented in the beam operation in 2024. After this upgrade, we could throw abnormal beams more than one turn earlier. It is a significant treatment against SBL. We report the details of the upgrade and the improved performance achieved in the 2024 operation.

JACOW
Openalex Percentile: Top 47%
Muon and positron interactions and applications
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.