LCLS-II commissioning and operation with high-repetition-rate CW FELs
LCLS-II first stage commissioning is completed in the summer of 2023, with demonstration of 93 kHz electron beam and 1 kHz FELs using the superconducting CW linac. Operation-based electron beam and FEL commissioning has been continued with the goal of ramping up beam rate, improving the FEL performance, and developing advanced FEL operation modes. We started 33 kHz x-ray FELs to user experiments from 2025. The latest machine performance, commissioning challenges, and next-step plan will be discussed in this paper