SLS 2.0 storage ring commissioning

The SLS consists of a 100MeV linac, a 2.7GeV booster synchrotron with 9nm horizontal emittance and the storage ring (SR). The old 12-TBA SR with 5nm horizontal emittance operating at 2.4GeV was turned off in 09/2023 after 22 years of successful user operation. In course of the SLS 2.0 upgrade project the 288m circumference SR has been replaced by a 2.7GeV 12-fold 7-bend achromat lattice with a considerably reduced horizontal emittance of 150pm, while keeping the injector complex mostly unchanged. After recommissioning of the injector chain at the end of 2024 SR commissioning starts in January 2025 with some challenges ahead. A reverse bend design has been implemented to achieve the lowest possible emittance with the given small footprint of the SR leading to a very dense magnet arrangement. All bending and combined function magnets which largely determine the novel optics are permanent magnets which will guide the beam through NEG coated vacuum tubes with an aperture of only 18mm. Due to excellent beam diagnostics and optics adjustment capabilities combined with an advanced remote girder alignment system we expect to achieve the performance goals of the storage ring by mid 2025.

Publication Details

Journal
JACOW
Published
2025-11-05
DOI
https://doi.org/10.18429/jacow-ipac2025-wecn1
Primary Topic
Particle Accelerators and Free-Electron Lasers
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

SLS 2.0 storage ring commissioning

JACOW
Particle Accelerators and Free-Electron Lasers
article

SLS 2.0 storage ring commissioning

article en

Abstract

The SLS consists of a 100MeV linac, a 2.7GeV booster synchrotron with 9nm horizontal emittance and the storage ring (SR). The old 12-TBA SR with 5nm horizontal emittance operating at 2.4GeV was turned off in 09/2023 after 22 years of successful user operation. In course of the SLS 2.0 upgrade project the 288m circumference SR has been replaced by a 2.7GeV 12-fold 7-bend achromat lattice with a considerably reduced horizontal emittance of 150pm, while keeping the injector complex mostly unchanged. After recommissioning of the injector chain at the end of 2024 SR commissioning starts in January 2025 with some challenges ahead. A reverse bend design has been implemented to achieve the lowest possible emittance with the given small footprint of the SR leading to a very dense magnet arrangement. All bending and combined function magnets which largely determine the novel optics are permanent magnets which will guide the beam through NEG coated vacuum tubes with an aperture of only 18mm. Due to excellent beam diagnostics and optics adjustment capabilities combined with an advanced remote girder alignment system we expect to achieve the performance goals of the storage ring by mid 2025.

JACOW
Openalex Percentile: Top 48%
Particle Accelerators and Free-Electron Lasers
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.