"Trade-off between renewable energy generation and environmental management in Rwanda: A case of Mushishito -Rukarara V hydropower plant in Nyamagabe District"

Fossil fuels contribute to environmental deterioration and climate change, necessitating environmental protection. Promoting sustainable energy sources like hydropower is crucial for addressing climate change and preserving natural resources, but their construction negatively impacts the hydrological landscape and raises concerns. The main objective of this study was to assess the trade-off between renewable energy generation and environmental management in Rwanda, Case of Rukarara V hydro power plant in Nyamagabe District. This study was guided by the following specific objectives: (i)To assess the environmental and social impacts value of the Mushishito-Rukarara V Hydropower Plant; (ii)To determine the costs and benefits of Mushishito-Rukarara V HP Plant in terms of energy generation and environmental protection.Significant attitudes were determined through structured interviews and site inspections using quantitative and qualitative methods. These findings were used to analyze project stages and actions, assessing environmental impacts and evaluating their relative importance. Author, revealed that the summation of positive and negative impacts of Mushishito-Rukarara V hydro power plant has reached to a value of -3 of EIV showing that the project's construction operations had a negligible negative influence on a number of environmental elements, and it was recommended that the project be approved with precautions taken to reduce any bad effects in order to ultimately reap greater advantages from it. The scenario analyzed focuses on financial returns, excluding environmental effects, with a Benefit-Cost Ratio of 1.84. The second scenario, with a Benefit-cost Ratio of 1.55, shows lower profit margin due to severe environmental impacts. The scenario analysis reveals that the Mushishito-Rukarara V HP project, despite its energy generation, does not compromise environmental conservation, benefiting both the project's owners and local communities.

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2025-08-28
DOI
https://doi.org/10.5281/zenodo.17470064
Primary Topic
Hydropower, Displacement, Environmental Impact
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

"Trade-off between renewable energy generation and environmental management in Rwanda: A case of Mushishito -Rukarara V hydropower plant in Nyamagabe District"

Zenodo (CERN European Organization for Nuclear Research)
Hydropower, Displacement, Environmental Impact
article

"Trade-off between renewable energy generation and environmental management in Rwanda: A case of Mushishito -Rukarara V hydropower plant in Nyamagabe District"

article en

Abstract

Fossil fuels contribute to environmental deterioration and climate change, necessitating environmental protection. Promoting sustainable energy sources like hydropower is crucial for addressing climate change and preserving natural resources, but their construction negatively impacts the hydrological landscape and raises concerns. The main objective of this study was to assess the trade-off between renewable energy generation and environmental management in Rwanda, Case of Rukarara V hydro power plant in Nyamagabe District. This study was guided by the following specific objectives: (i)To assess the environmental and social impacts value of the Mushishito-Rukarara V Hydropower Plant; (ii)To determine the costs and benefits of Mushishito-Rukarara V HP Plant in terms of energy generation and environmental protection.Significant attitudes were determined through structured interviews and site inspections using quantitative and qualitative methods. These findings were used to analyze project stages and actions, assessing environmental impacts and evaluating their relative importance. Author, revealed that the summation of positive and negative impacts of Mushishito-Rukarara V hydro power plant has reached to a value of -3 of EIV showing that the project's construction operations had a negligible negative influence on a number of environmental elements, and it was recommended that the project be approved with precautions taken to reduce any bad effects in order to ultimately reap greater advantages from it. The scenario analyzed focuses on financial returns, excluding environmental effects, with a Benefit-Cost Ratio of 1.84. The second scenario, with a Benefit-cost Ratio of 1.55, shows lower profit margin due to severe environmental impacts. The scenario analysis reveals that the Mushishito-Rukarara V HP project, despite its energy generation, does not compromise environmental conservation, benefiting both the project's owners and local communities.

Zenodo (CERN European Organization for Nuclear Research)
Life in Land
Openalex Percentile: Top 35%
Hydropower, Displacement, Environmental Impact
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

"Trade-off between renewable energy generation and environmental management in Rwanda: A case of Mushishito -Rukarara V hydropower plant in Nyamagabe District" · Zenodo (CERN European Organization for Nuclear Research) (2025) | TGRS Research Map | TGRS