Reliable Delivery Order for Improving Workflow in the Construction Supply Chain

Achieving reliable workflow on-site has long been a priority in the lean construction community, particularly as construction projects become more complex and uncertain.A reliable supply chain between an external supplier and on-site contractor becomes even more critical to project success as the architecture, engineering, and construction (AEC) industry increasingly adopts prefabrication and off-site construction.This paper addresses the increasing need for a reliable supply chain by focusing on ensuring the reliability of delivery orders.Recent studies on construction supply chains have attested that demand uncertainty leads to diminished reliability in the product flow of the supply chain, more so when external suppliers are not shielded against the uncertainty in the delivery due date.This paper introduces a systematic approach to enhancing delivery order reliability by applying the Last Planner to the order-releasing process.In this paper, we present a set of strategies to improve delivery order reliability, including organizational and contractual structures at the organizational level, supplier involvement in construction scheduling at the project level, and ensuring high-quality delivery orders at the process level.Moreover, we introduce three key quality criteria to enhance delivery order reliability as well as a set of metrics to measure delivery order reliability effectively, specifically DOR(%) and DOR() as a probabilistic distribution.

Publication Details

Journal
Annual Conference of the International Group for Lean Construction
Published
2025-06-02
DOI
https://doi.org/10.24928/2025/0206
Primary Topic
Atmospheric aerosols and clouds
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Reliable Delivery Order for Improving Workflow in the Construction Supply Chain

Annual Conference of the International Group for Lean Construction
Atmospheric aerosols and clouds
article

Reliable Delivery Order for Improving Workflow in the Construction Supply Chain

article en

Abstract

Achieving reliable workflow on-site has long been a priority in the lean construction community, particularly as construction projects become more complex and uncertain.A reliable supply chain between an external supplier and on-site contractor becomes even more critical to project success as the architecture, engineering, and construction (AEC) industry increasingly adopts prefabrication and off-site construction.This paper addresses the increasing need for a reliable supply chain by focusing on ensuring the reliability of delivery orders.Recent studies on construction supply chains have attested that demand uncertainty leads to diminished reliability in the product flow of the supply chain, more so when external suppliers are not shielded against the uncertainty in the delivery due date.This paper introduces a systematic approach to enhancing delivery order reliability by applying the Last Planner to the order-releasing process.In this paper, we present a set of strategies to improve delivery order reliability, including organizational and contractual structures at the organizational level, supplier involvement in construction scheduling at the project level, and ensuring high-quality delivery orders at the process level.Moreover, we introduce three key quality criteria to enhance delivery order reliability as well as a set of metrics to measure delivery order reliability effectively, specifically DOR(%) and DOR() as a probabilistic distribution.

Annual Conference of the International Group for Lean Construction
Openalex Percentile: Top 27%
Atmospheric aerosols and clouds
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Reliable Delivery Order for Improving Workflow in the Construction Supply Chain · Annual Conference of the International Group for Lean Construction (2025) | TGRS Research Map | TGRS