ANALISIS PENGENDALIAN WAKTU DAN BIAYA DENGAN METODE EARNED VALUE MANAGEMENT (EVM)

It is often found that projects experience delays in completion during their implementation in the field. Project control is very necessary because it affects the success of a project. The aim of this research is to evaluate time and cost control in the Palembang Ministry of Health Polytechnic Academic Services Building Project using the Earned Value Management method. This method analyzes time and cost deviations through Cost Variance and Schedule Variance. To assess the efficiency of resource use using the Cost Performance Index and Schedule Performance Index, and to analyze estimated costs and project completion time through ETC and EAC, as well as ETS and EAS. The research results show that the schedule performance index value shows an average SPI value > 1 which indicates that the project is running faster than the planned schedule, then the cost performance index is also CPI > 1 indicating good and economical use of cost performance. This project was successfully completed 100% 2 weeks ahead of schedule. The ETC value obtained at week 26 is zero (0), which means the budget has been exhausted and the work has been completed. The EAC value obtained is the same as the ACWP value, namely IDR 20,685,524,900.00, which shows that the project is proceeding according to the planned cost and schedule. Despite some delays in certain weeks, this case study shows that EVM is an effective method for controlling construction project time and costs.

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-08-08
DOI
https://doi.org/10.25157/mediailmiahtekniksipil.v2i2.4298
Primary Topic
Agriculture Sustainability and Environmental Impact
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS PENGENDALIAN WAKTU DAN BIAYA DENGAN METODE EARNED VALUE MANAGEMENT (EVM)

Jurnal Ilmiah Teknik Sipil
Agriculture Sustainability and Environmental Impact
article

ANALISIS PENGENDALIAN WAKTU DAN BIAYA DENGAN METODE EARNED VALUE MANAGEMENT (EVM)

article en

Abstract

It is often found that projects experience delays in completion during their implementation in the field. Project control is very necessary because it affects the success of a project. The aim of this research is to evaluate time and cost control in the Palembang Ministry of Health Polytechnic Academic Services Building Project using the Earned Value Management method. This method analyzes time and cost deviations through Cost Variance and Schedule Variance. To assess the efficiency of resource use using the Cost Performance Index and Schedule Performance Index, and to analyze estimated costs and project completion time through ETC and EAC, as well as ETS and EAS. The research results show that the schedule performance index value shows an average SPI value > 1 which indicates that the project is running faster than the planned schedule, then the cost performance index is also CPI > 1 indicating good and economical use of cost performance. This project was successfully completed 100% 2 weeks ahead of schedule. The ETC value obtained at week 26 is zero (0), which means the budget has been exhausted and the work has been completed. The EAC value obtained is the same as the ACWP value, namely IDR 20,685,524,900.00, which shows that the project is proceeding according to the planned cost and schedule. Despite some delays in certain weeks, this case study shows that EVM is an effective method for controlling construction project time and costs.

Jurnal Ilmiah Teknik SipilVol. 2(2)
Universitas Galuh (ID)
Decent work and economic growth
Openalex Percentile: Top 43%
Agriculture Sustainability and Environmental Impact
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

ANALISIS PENGENDALIAN WAKTU DAN BIAYA DENGAN METODE EARNED VALUE MANAGEMENT (EVM) · Jurnal Ilmiah Teknik Sipil (2025) | TGRS Research Map | TGRS