Evaluasi Pengendalian Waktu menggunakan Metode Earned Value Management (EVM) (Studi kasus: Konstruksi Fisik Pembangunan Gedung Parkir Sepeda Motor)

Time control is a crucial aspect in construction project management, especially in motorbike parking building construction projects. This research aims to evaluate the effectiveness of time control using the Earned Value Management (EVM) method. EVM is used to analyze project performance based on a comparison between planned value, earned value and actual costs. Through a case study approach, data was obtained from the ongoing physical construction project for the construction of a motorbike parking building. The analysis results show that EVM is effective in identifying time variance and project schedule efficiency, through measuring schedule variance (SV) and schedule performance index (SPI). These indicators provide important information to project management to take timely corrective action, to ensure the project runs according to the established schedule. In conclusion, the application of the EVM method can increase the effectiveness of time control and help manage construction projects in a more measurable and structured manner.

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-08-08
DOI
https://doi.org/10.25157/mediailmiahtekniksipil.v2i2.4316
Primary Topic
Geochemistry and Geologic Mapping
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Evaluasi Pengendalian Waktu menggunakan Metode Earned Value Management (EVM) (Studi kasus: Konstruksi Fisik Pembangunan Gedung Parkir Sepeda Motor)

Jurnal Ilmiah Teknik Sipil
Geochemistry and Geologic Mapping
article

Evaluasi Pengendalian Waktu menggunakan Metode Earned Value Management (EVM) (Studi kasus: Konstruksi Fisik Pembangunan Gedung Parkir Sepeda Motor)

article en

Abstract

Time control is a crucial aspect in construction project management, especially in motorbike parking building construction projects. This research aims to evaluate the effectiveness of time control using the Earned Value Management (EVM) method. EVM is used to analyze project performance based on a comparison between planned value, earned value and actual costs. Through a case study approach, data was obtained from the ongoing physical construction project for the construction of a motorbike parking building. The analysis results show that EVM is effective in identifying time variance and project schedule efficiency, through measuring schedule variance (SV) and schedule performance index (SPI). These indicators provide important information to project management to take timely corrective action, to ensure the project runs according to the established schedule. In conclusion, the application of the EVM method can increase the effectiveness of time control and help manage construction projects in a more measurable and structured manner.

Jurnal Ilmiah Teknik SipilVol. 2(2)
Universitas Galuh (ID)
Openalex Percentile: Top 27%
Geochemistry and Geologic Mapping
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Evaluasi Pengendalian Waktu menggunakan Metode Earned Value Management (EVM) (Studi kasus: Konstruksi Fisik Pembangunan Gedung Parkir Sepeda Motor) · Jurnal Ilmiah Teknik Sipil (2025) | TGRS Research Map | TGRS