ANALISIS ESTIMASI WAKTU DAN BIAYA MENGGUNAKAN METODE EARNED VALUE ANALYSIS

ABSTRACT Estimation of project time and costs is part of construction management. The achievement of a project can also be assessed from the estimated time and cost of completing the project. The Tasikmalaya Regency Cultural Center Gallery Building Construction Project was completed at a cost and time that exceeded the plan, therefore it is necessary to evaluate and analyze project cost and time estimates to obtain the cheapest and fastest cost and completion time with maximum results. Analysis of estimated costs and time in the Gallery Building Development Project in the Cultural Center (Case Study of Kp. Balananjeur, Pagersari Village, Pagerageung District, Tasikmalaya Regency) uses the Earned Value Analysis (EVA) method. The method used in this research is descriptive quantitative, the research describes the condition of the project by analyzing existing data. Data analysis used analytical and descriptive methods. Analytical, that is, existing data is processed using Earned Value Analysis (EVA) to produce conclusive final results. While descriptive is by describing the problems that already exist or appear. The results of the time performance research on the Tasikmalaya Regency Cultural Center Gallery Building Construction Project are not good with an average time performance index (SPI) of 0.997 < 1 and cost performance (CPI) of 0.997 < 1, this indicates that the performance of time and costs is not good, because the work is not as expected and unable to achieve the planned work targets. The difference in time and cost to complete the Tasikmalaya Regency Cultural Center Gallery Building Project is Rp. 19,918,900.00, - and an additional 11 working days. Keywords : Time Estimation, Earned Value Analysis, Time Performance

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-08-08
DOI
https://doi.org/10.25157/mediailmiahtekniksipil.v2i2.3382
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS ESTIMASI WAKTU DAN BIAYA MENGGUNAKAN METODE EARNED VALUE ANALYSIS

Jurnal Ilmiah Teknik Sipil
Occupational Health and Safety Management
article

ANALISIS ESTIMASI WAKTU DAN BIAYA MENGGUNAKAN METODE EARNED VALUE ANALYSIS

article en

Abstract

ABSTRACT Estimation of project time and costs is part of construction management. The achievement of a project can also be assessed from the estimated time and cost of completing the project. The Tasikmalaya Regency Cultural Center Gallery Building Construction Project was completed at a cost and time that exceeded the plan, therefore it is necessary to evaluate and analyze project cost and time estimates to obtain the cheapest and fastest cost and completion time with maximum results. Analysis of estimated costs and time in the Gallery Building Development Project in the Cultural Center (Case Study of Kp. Balananjeur, Pagersari Village, Pagerageung District, Tasikmalaya Regency) uses the Earned Value Analysis (EVA) method. The method used in this research is descriptive quantitative, the research describes the condition of the project by analyzing existing data. Data analysis used analytical and descriptive methods. Analytical, that is, existing data is processed using Earned Value Analysis (EVA) to produce conclusive final results. While descriptive is by describing the problems that already exist or appear. The results of the time performance research on the Tasikmalaya Regency Cultural Center Gallery Building Construction Project are not good with an average time performance index (SPI) of 0.997 < 1 and cost performance (CPI) of 0.997 < 1, this indicates that the performance of time and costs is not good, because the work is not as expected and unable to achieve the planned work targets. The difference in time and cost to complete the Tasikmalaya Regency Cultural Center Gallery Building Project is Rp. 19,918,900.00, - and an additional 11 working days. Keywords : Time Estimation, Earned Value Analysis, Time Performance

Jurnal Ilmiah Teknik SipilVol. 2(2)
Universitas Galuh (ID)
Sustainable cities and communities
Openalex Percentile: Top 34%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

ANALISIS ESTIMASI WAKTU DAN BIAYA MENGGUNAKAN METODE EARNED VALUE ANALYSIS · Jurnal Ilmiah Teknik Sipil (2025) | TGRS Research Map | TGRS