ANALISIS PENGENDALIAN WAKTU DENGAN METODE PERT (PROGRAM EVALUATION AND REVIEW TECHNIQUE) PADA PROYEK PENGGANTIAN JEMBATAN CIBUYUT RUAS JALAN KAWALI – SADANANYA KECAMATAN CIPAKU KABUPATEN CIAMIS

Project generally have a deadline, meaning the project must be completed before or exactly at the speciefied time. In connection with project problem, delays occurred in the Cibuyut Bridge Replacment Project for Jalan Kawali – Sadananya. The aim of this research is to rescheadule using the Program Evaluation Review Technique (PERT) method. The methode used in this research to estimate three times, namely optimistic time, pessimistic time and most likely/realistic time. The research uses a descriptive analysis using network technique. From the analysis results it was found that the critical path is a series of activities 2-3-7-14-18-19 with the expected time to carry out project being 101 days. Meanwhile, in the actual time schedule the project takes 120 days. The value (probabilty) of the project being completed on the planned time (101 days) is 93,06%. The project can be completed on time if there are no delays.

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-02-07
DOI
https://doi.org/10.25157/mediailmiahtekniksipil.v2i1.4111
Primary Topic
Landfill Environmental Impact Studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS PENGENDALIAN WAKTU DENGAN METODE PERT (PROGRAM EVALUATION AND REVIEW TECHNIQUE) PADA PROYEK PENGGANTIAN JEMBATAN CIBUYUT RUAS JALAN KAWALI – SADANANYA KECAMATAN CIPAKU KABUPATEN CIAMIS

Jurnal Ilmiah Teknik Sipil
Landfill Environmental Impact Studies
article

ANALISIS PENGENDALIAN WAKTU DENGAN METODE PERT (PROGRAM EVALUATION AND REVIEW TECHNIQUE) PADA PROYEK PENGGANTIAN JEMBATAN CIBUYUT RUAS JALAN KAWALI – SADANANYA KECAMATAN CIPAKU KABUPATEN CIAMIS

article en

Abstract

Project generally have a deadline, meaning the project must be completed before or exactly at the speciefied time. In connection with project problem, delays occurred in the Cibuyut Bridge Replacment Project for Jalan Kawali – Sadananya. The aim of this research is to rescheadule using the Program Evaluation Review Technique (PERT) method. The methode used in this research to estimate three times, namely optimistic time, pessimistic time and most likely/realistic time. The research uses a descriptive analysis using network technique. From the analysis results it was found that the critical path is a series of activities 2-3-7-14-18-19 with the expected time to carry out project being 101 days. Meanwhile, in the actual time schedule the project takes 120 days. The value (probabilty) of the project being completed on the planned time (101 days) is 93,06%. The project can be completed on time if there are no delays.

Jurnal Ilmiah Teknik SipilVol. 2(1)
Universitas Galuh (ID)
Openalex Percentile: Top 46%
Landfill Environmental Impact Studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.