ANALISIS WAKTU DAN BIAYA PADA PROYEK PENINGKATAN JALAN LINGKUNGAN RUNGKI KELURAHAN CIGEMBOR MENGGUNAKAN METODE CPM

Generally, a project has a deadline, which means that the project must be completed before or exactly at a predetermined time. In the Rungki Environmental Road Improvement Project, Cigembor Village, in its implementation, it experienced delays which resulted in an increase in the duration of the project. This research uses the CPM (Critical Path Method), by analyzing data to find the critical trajectory so that it can be known the optimal duration and what work is on the critical trajectory as well as cost estimation with the addition of working hours. The results of the research on the Rungki Environmental Road Improvement Project in Cigembor Village took 28 days, after analysis using the CPM method and the duration acceleration with crashing obtained a duration of 19 days with an acceleration difference of 9 days. The estimated cost required for this project with the addition of working hours (overtime) for 3 hours there is an additional cost of Rp.70.628.039,47

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-02-07
DOI
https://doi.org/10.25157/mediailmiahtekniksipil.v2i1.3396
Primary Topic
Canadian Policy and Governance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS WAKTU DAN BIAYA PADA PROYEK PENINGKATAN JALAN LINGKUNGAN RUNGKI KELURAHAN CIGEMBOR MENGGUNAKAN METODE CPM

Jurnal Ilmiah Teknik Sipil
Canadian Policy and Governance
article

ANALISIS WAKTU DAN BIAYA PADA PROYEK PENINGKATAN JALAN LINGKUNGAN RUNGKI KELURAHAN CIGEMBOR MENGGUNAKAN METODE CPM

article en

Abstract

Generally, a project has a deadline, which means that the project must be completed before or exactly at a predetermined time. In the Rungki Environmental Road Improvement Project, Cigembor Village, in its implementation, it experienced delays which resulted in an increase in the duration of the project. This research uses the CPM (Critical Path Method), by analyzing data to find the critical trajectory so that it can be known the optimal duration and what work is on the critical trajectory as well as cost estimation with the addition of working hours. The results of the research on the Rungki Environmental Road Improvement Project in Cigembor Village took 28 days, after analysis using the CPM method and the duration acceleration with crashing obtained a duration of 19 days with an acceleration difference of 9 days. The estimated cost required for this project with the addition of working hours (overtime) for 3 hours there is an additional cost of Rp.70.628.039,47

Jurnal Ilmiah Teknik SipilVol. 2(1)
Universitas Galuh (ID)
Sustainable cities and communities
Openalex Percentile: Top 39%
Canadian Policy and Governance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

ANALISIS WAKTU DAN BIAYA PADA PROYEK PENINGKATAN JALAN LINGKUNGAN RUNGKI KELURAHAN CIGEMBOR MENGGUNAKAN METODE CPM · Jurnal Ilmiah Teknik Sipil (2025) | TGRS Research Map | TGRS