EVALUASI PENGENDALIAN WAKTU DAN BIAYA DENGAN METODE EARNED VALUE MANAGEMENT (EVM)

Problems in the Tarikolot Sidamulih Pangandaran Road Improvement Project delay in completing work so that time and cost trends not in accordance with the plan. It is necessary to evaluate the time and cost control on the Tarikolot Road Improvement Project Sidamulih Pangandaran using the Earned Value Management method (EVM). The EVM method can integrate time and cost factors in control of construction projects. The purpose of this study is to determine the control of time and cost in Tarikolot Sidamulih Pangandaran Road Improvement Project with using the Earned Value Management (EVM) method. Methods that used in this study is quantitative descriptive, research describe the condition of the project with the analysis of existing data. Data analysis using analytical and descriptive methods. Analytics is existing data processed in such a way as to produce a final result that can Concluded. While descriptive, namely by explaining the problems that already exists or appears. The results of the study show that the Earned Value Management (EVM) method can control the time and cost of the Tarikolot Road Improvement Project Sidamulih Pangandaran. This is shown from the average value of the time performance index (SPI) more than one, this shows that the time performance is quite good, so that work is in accordance with expectations because it is able to achieve the target work that has been planned. Greater cost performance index (CPI) value From one, this shows that the cost performance is very good, because the cost of (Actual Cost) is smaller when compared to the value (Earned Value) or there is no waste.

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-08-08
DOI
https://doi.org/10.25157/mediailmiahtekniksipil.v2i2.4336
Primary Topic
Geochemistry and Geologic Mapping
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

EVALUASI PENGENDALIAN WAKTU DAN BIAYA DENGAN METODE EARNED VALUE MANAGEMENT (EVM)

Jurnal Ilmiah Teknik Sipil
Geochemistry and Geologic Mapping
article

EVALUASI PENGENDALIAN WAKTU DAN BIAYA DENGAN METODE EARNED VALUE MANAGEMENT (EVM)

article en

Abstract

Problems in the Tarikolot Sidamulih Pangandaran Road Improvement Project delay in completing work so that time and cost trends not in accordance with the plan. It is necessary to evaluate the time and cost control on the Tarikolot Road Improvement Project Sidamulih Pangandaran using the Earned Value Management method (EVM). The EVM method can integrate time and cost factors in control of construction projects. The purpose of this study is to determine the control of time and cost in Tarikolot Sidamulih Pangandaran Road Improvement Project with using the Earned Value Management (EVM) method. Methods that used in this study is quantitative descriptive, research describe the condition of the project with the analysis of existing data. Data analysis using analytical and descriptive methods. Analytics is existing data processed in such a way as to produce a final result that can Concluded. While descriptive, namely by explaining the problems that already exists or appears. The results of the study show that the Earned Value Management (EVM) method can control the time and cost of the Tarikolot Road Improvement Project Sidamulih Pangandaran. This is shown from the average value of the time performance index (SPI) more than one, this shows that the time performance is quite good, so that work is in accordance with expectations because it is able to achieve the target work that has been planned. Greater cost performance index (CPI) value From one, this shows that the cost performance is very good, because the cost of (Actual Cost) is smaller when compared to the value (Earned Value) or there is no waste.

Jurnal Ilmiah Teknik SipilVol. 2(2)
Universitas Galuh (ID)
Openalex Percentile: Top 27%
Geochemistry and Geologic Mapping
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

EVALUASI PENGENDALIAN WAKTU DAN BIAYA DENGAN METODE EARNED VALUE MANAGEMENT (EVM) · Jurnal Ilmiah Teknik Sipil (2025) | TGRS Research Map | TGRS