EVALUASI PENGENDALIAN BIAYA MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (EVM) PADA PROYEK REVITALISASI SDN SUKAMAJU KECAMATAN PANCATENGAH KABUPATEN TASIKMALAYA

Evaluation of cost control using the Earned Value Management (EVM) method in revitalization projects is important to identify budget and schedule deviations early on, so that corrective actions can be taken to ensure the project runs according to plan. This study aims to determine the performance of project costs and the estimated final cost of the SDN Sukamaju Revitalization project, Pancatengah District, Tasikmalaya Regency using the Earned Value Management (EVM) method. The method used in this study is quantitative descriptive by collecting data and information from the implementation of the SDN Sukamaju Revitalization project, Pancatengah District, Tasikmalaya Regency. Project cost and schedule data that have been running are analyzed using EVM indicators, including Planned Value (PV), Earned Value (EV), and Actual Cost (AC). The results of the study indicate that the use of the EVM method provides a clear picture of project performance, identifies deviations from the planned budget, and provides guidance for project managers to take corrective actions. With EVM, projects can be controlled more effectively to achieve goals within the specified time and budget limits

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-08-08
DOI
https://doi.org/10.25157/mediailmiahtekniksipil.v2i2.4287
Primary Topic
Economic, Social, and Health Studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

EVALUASI PENGENDALIAN BIAYA MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (EVM) PADA PROYEK REVITALISASI SDN SUKAMAJU KECAMATAN PANCATENGAH KABUPATEN TASIKMALAYA

Jurnal Ilmiah Teknik Sipil
Economic, Social, and Health Studies
article

EVALUASI PENGENDALIAN BIAYA MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (EVM) PADA PROYEK REVITALISASI SDN SUKAMAJU KECAMATAN PANCATENGAH KABUPATEN TASIKMALAYA

article en

Abstract

Evaluation of cost control using the Earned Value Management (EVM) method in revitalization projects is important to identify budget and schedule deviations early on, so that corrective actions can be taken to ensure the project runs according to plan. This study aims to determine the performance of project costs and the estimated final cost of the SDN Sukamaju Revitalization project, Pancatengah District, Tasikmalaya Regency using the Earned Value Management (EVM) method. The method used in this study is quantitative descriptive by collecting data and information from the implementation of the SDN Sukamaju Revitalization project, Pancatengah District, Tasikmalaya Regency. Project cost and schedule data that have been running are analyzed using EVM indicators, including Planned Value (PV), Earned Value (EV), and Actual Cost (AC). The results of the study indicate that the use of the EVM method provides a clear picture of project performance, identifies deviations from the planned budget, and provides guidance for project managers to take corrective actions. With EVM, projects can be controlled more effectively to achieve goals within the specified time and budget limits

Jurnal Ilmiah Teknik SipilVol. 2(2)
Universitas Galuh (ID)
Partnerships for the goals
Openalex Percentile: Top 35%
Economic, Social, and Health Studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.