ANALISIS PERBANDINGAN PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK KONTRUKSI MENGGUNAKAN CRITICAL PATH METHODE (CPM) DAN PRECEDENCE DIAGRAM METHODE (PDM)

The Linggasari road improvement project, Linggapura village, Kawali District, Ciamis Regency, in the implementation process there was a delay in Laston Lapis AUS Laveling (AC-WC) work so that the work experienced problems in its implementation time. This study aims to determine the comparison of schedules in construction projects using the Critical Path Method (CPM) and Predecence Diagram Method (PDM) methods. In the Cost Budget Plan, this project requires a cost of Rp. 2,116,414,876.33. After an acceleration analysis was carried out on the critical path by adding overtime hours for 3 hours per day using the CPM method, the total project became IDR 2,193,045,306.97 or with a cost difference of IDR 75,085,896.64. Meanwhile, the analysis of acceleration on the critical path by adding overtime hours for 3 hours per day with the PDM method total projects to IDR 2,193,045,306.9 or with a cost difference of IDR 76,630,458.56. Based on the actual time schedule, the Linggasari Road Improvement Project, Linggapura Village, Kawali District, Ciamis Regency takes 33 working days, while after analysis using the Critical Path Method (CPM), the construction runs 23 days, which is 10 days faster and uses the Precedence Diagram Method (PDM) to 22 days, which is 11 days faster than implementation. The Linggasari road improvement project, Linggapura village, Kawali District, Ciamis Regency, in the implementation process there was a delay in Laston Lapis AUS Laveling (AC-WC) work so that the work experienced problems in its implementation time. This study aims to determine the comparison of schedules in construction projects using the Critical Path Method (CPM) and Predecence Diagram Method (PDM) methods. In the Cost Budget Plan, this project requires a cost of Rp. 2,116,414,876.33. After an acceleration analysis was carried out on the critical path by adding overtime hours for 3 hours per day using the CPM method, the total project became IDR 2,193,045,306.97 or with a cost difference of IDR 75,085,896.64. Meanwhile, the analysis of acceleration on the critical path by adding overtime hours for 3 hours per day with the PDM method total projects to IDR 2,193,045,306.9 or with a cost difference of IDR 76,630,458.56. Based on the actual time schedule, the Linggasari Road Improvement Project, Linggapura Village, Kawali District, Ciamis Regency takes 33 working days, while after analysis using the Critical Path Method (CPM), the construction runs 23 days, which is 10 days faster and uses the Precedence Diagram Method (PDM) to 22 days, which is 11 days faster than implementation.

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-02-07
DOI
https://doi.org/10.25157/mediailmiahtekniksipil.v2i1.3561
Primary Topic
Anarchism and Radical Politics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS PERBANDINGAN PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK KONTRUKSI MENGGUNAKAN CRITICAL PATH METHODE (CPM) DAN PRECEDENCE DIAGRAM METHODE (PDM)

Jurnal Ilmiah Teknik Sipil
Anarchism and Radical Politics
article

ANALISIS PERBANDINGAN PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK KONTRUKSI MENGGUNAKAN CRITICAL PATH METHODE (CPM) DAN PRECEDENCE DIAGRAM METHODE (PDM)

article en

Abstract

The Linggasari road improvement project, Linggapura village, Kawali District, Ciamis Regency, in the implementation process there was a delay in Laston Lapis AUS Laveling (AC-WC) work so that the work experienced problems in its implementation time. This study aims to determine the comparison of schedules in construction projects using the Critical Path Method (CPM) and Predecence Diagram Method (PDM) methods. In the Cost Budget Plan, this project requires a cost of Rp. 2,116,414,876.33. After an acceleration analysis was carried out on the critical path by adding overtime hours for 3 hours per day using the CPM method, the total project became IDR 2,193,045,306.97 or with a cost difference of IDR 75,085,896.64. Meanwhile, the analysis of acceleration on the critical path by adding overtime hours for 3 hours per day with the PDM method total projects to IDR 2,193,045,306.9 or with a cost difference of IDR 76,630,458.56. Based on the actual time schedule, the Linggasari Road Improvement Project, Linggapura Village, Kawali District, Ciamis Regency takes 33 working days, while after analysis using the Critical Path Method (CPM), the construction runs 23 days, which is 10 days faster and uses the Precedence Diagram Method (PDM) to 22 days, which is 11 days faster than implementation. The Linggasari road improvement project, Linggapura village, Kawali District, Ciamis Regency, in the implementation process there was a delay in Laston Lapis AUS Laveling (AC-WC) work so that the work experienced problems in its implementation time. This study aims to determine the comparison of schedules in construction projects using the Critical Path Method (CPM) and Predecence Diagram Method (PDM) methods. In the Cost Budget Plan, this project requires a cost of Rp. 2,116,414,876.33. After an acceleration analysis was carried out on the critical path by adding overtime hours for 3 hours per day using the CPM method, the total project became IDR 2,193,045,306.97 or with a cost difference of IDR 75,085,896.64. Meanwhile, the analysis of acceleration on the critical path by adding overtime hours for 3 hours per day with the PDM method total projects to IDR 2,193,045,306.9 or with a cost difference of IDR 76,630,458.56. Based on the actual time schedule, the Linggasari Road Improvement Project, Linggapura Village, Kawali District, Ciamis Regency takes 33 working days, while after analysis using the Critical Path Method (CPM), the construction runs 23 days, which is 10 days faster and uses the Precedence Diagram Method (PDM) to 22 days, which is 11 days faster than implementation.

Jurnal Ilmiah Teknik SipilVol. 2(1)
Universitas Galuh (ID)
Openalex Percentile: Top 37%
Anarchism and Radical Politics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.