ANALISIS BIAYA DAN WAKTU DENGAN METODE TIME COST TRADE OFF (TCTO)

The implementation of the Rumah Susun Jawa Barat 2 (RSNPP-21-02-JBR) Ponpes Hidayatul Ulum Tasikmalaya City project is experiencing delays, so it is necessary to analyze the rescheduling. The method that can be used is the Time Cost Trade Off (TCTO) method or it can also be called the exchange method between cost and time. The purpose of this study was to determine the acceleration time and cost required to complete the work on the Rumah Susun Jawa Barat 2 Construction project (RSNPP-21-02-JBR) Ponpes Hidayatul Ulum Tasikmalaya City in accordance with the plan by applying the Time Cost Trade Off (TCTO) method. The research results from rescheduling by applying the TCTO (Time Cost Trade Off) method for an additional 1 hour the amount of duration that can be accelerated is 12 working days, which was originally 115 working days to 103 working days. With a project time efficiency of 11.14% with an optimum cost of Rp. 851,881,506.21 from Rp. 856,366,913.45 with a difference of Rp. 4,485,407.25. As for the addition of 2 hours, the amount of duration that can be accelerated is 19 working days, which was originally 115 working days to 96 working days. With a project time efficiency of 19.791% with an optimum cost of Rp. 854,252,465.85 from Rp. 856,366,913.45 with a difference of Rp. 2,114,447.61.

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-08-08
DOI
https://doi.org/10.25157/mediailmiahtekniksipil.v2i2.4431
Primary Topic
Geochemistry and Geologic Mapping
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS BIAYA DAN WAKTU DENGAN METODE TIME COST TRADE OFF (TCTO)

Jurnal Ilmiah Teknik Sipil
Geochemistry and Geologic Mapping
article

ANALISIS BIAYA DAN WAKTU DENGAN METODE TIME COST TRADE OFF (TCTO)

article en

Abstract

The implementation of the Rumah Susun Jawa Barat 2 (RSNPP-21-02-JBR) Ponpes Hidayatul Ulum Tasikmalaya City project is experiencing delays, so it is necessary to analyze the rescheduling. The method that can be used is the Time Cost Trade Off (TCTO) method or it can also be called the exchange method between cost and time. The purpose of this study was to determine the acceleration time and cost required to complete the work on the Rumah Susun Jawa Barat 2 Construction project (RSNPP-21-02-JBR) Ponpes Hidayatul Ulum Tasikmalaya City in accordance with the plan by applying the Time Cost Trade Off (TCTO) method. The research results from rescheduling by applying the TCTO (Time Cost Trade Off) method for an additional 1 hour the amount of duration that can be accelerated is 12 working days, which was originally 115 working days to 103 working days. With a project time efficiency of 11.14% with an optimum cost of Rp. 851,881,506.21 from Rp. 856,366,913.45 with a difference of Rp. 4,485,407.25. As for the addition of 2 hours, the amount of duration that can be accelerated is 19 working days, which was originally 115 working days to 96 working days. With a project time efficiency of 19.791% with an optimum cost of Rp. 854,252,465.85 from Rp. 856,366,913.45 with a difference of Rp. 2,114,447.61.

Jurnal Ilmiah Teknik SipilVol. 2(2)
Universitas Galuh (ID)
Sustainable cities and communities
Openalex Percentile: Top 27%
Geochemistry and Geologic Mapping
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.