Analisis Manajemen Waktu Pada Pembangunan Perumahan Zahwa Residence Kota Banjar Menggunakan Metode Critical Path Mthod (CPM)

Planning in project time is one way to control the execution of work which is an essential path of every project activity. Project failure will be even greater without optimal time management. In every project implementation, it is necessary to handle good project scheduling management. A project is said to be good if the completion of the project is efficient in terms of time, then a way is needed so that the completion of the structure of the house can be done quickly to meet the needs of the community.The purpose of this research is to find out the critical activities and the total duration of the Zahwa Residence Housing Project in Banjar City using the CPM (Critical Path Method). The data used are primary data and secondary data.The results of research on the Zahwa Residence type 36 housing development project using the critical path method obtained a critical path with symbols A, E, F, G, H, M, N, P, Q and B,C,D,I. The results of the normal duration comparison, the analysis of the critical path method and the normal duration value are 30 days, the analysis value of the critical path method is 25 days.

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-08-08
DOI
https://doi.org/10.25157/mediailmiahtekniksipil.v2i2.3480
Primary Topic
Canadian Policy and Governance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analisis Manajemen Waktu Pada Pembangunan Perumahan Zahwa Residence Kota Banjar Menggunakan Metode Critical Path Mthod (CPM)

Jurnal Ilmiah Teknik Sipil
Canadian Policy and Governance
article

Analisis Manajemen Waktu Pada Pembangunan Perumahan Zahwa Residence Kota Banjar Menggunakan Metode Critical Path Mthod (CPM)

article en

Abstract

Planning in project time is one way to control the execution of work which is an essential path of every project activity. Project failure will be even greater without optimal time management. In every project implementation, it is necessary to handle good project scheduling management. A project is said to be good if the completion of the project is efficient in terms of time, then a way is needed so that the completion of the structure of the house can be done quickly to meet the needs of the community.The purpose of this research is to find out the critical activities and the total duration of the Zahwa Residence Housing Project in Banjar City using the CPM (Critical Path Method). The data used are primary data and secondary data.The results of research on the Zahwa Residence type 36 housing development project using the critical path method obtained a critical path with symbols A, E, F, G, H, M, N, P, Q and B,C,D,I. The results of the normal duration comparison, the analysis of the critical path method and the normal duration value are 30 days, the analysis value of the critical path method is 25 days.

Jurnal Ilmiah Teknik SipilVol. 2(2)
Universitas Galuh (ID)
Sustainable cities and communities
Openalex Percentile: Top 39%
Canadian Policy and Governance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.