Dispute Review Boards: Using the Law as a Guide in Settling Construction Contract Disputes

In the spring of 2017, a contractor submitted a Notice of Intent (NOI) to file a claim for additional compensation for implementation of “100% pile driving analysis (PDA)” on the production piles to achieve the required bearing capacity in Bents #5 and #6 of a bridge being constructed as part of a project to widen and improve a major thoroughfare in Pensacola, Florida. In the summer of that same year, the contractor submitted another NOI to file a separate claim for additional compensation for implementation of 100% PDA on the production piles in Bents #1, #2, and #3 of the same project. The contractor claimed that, based on geotechnical reports provided by Florida Department of Transportation, they (the contractor) did not expect to have to use the PDA, and thus did not bid the job to include the PDA; therefore, their having to employ the PDA was “unforeseeable work.” When the parties could not reach agreement, both parties requested a hearing be conducted by the Disputes Review Board (DRB) assigned to that project. The hearing focused on both claims. At the hearing’s conclusion, in a unanimous decision, the Board recommended “ENTITLEMENT” for the contractor. This paper offers insight into the progression of the DRB process from the beginning of the project to the conclusion of the hearing, as executed by one of the oldest and best-established DRB programs in the US.

Institutions

Publication Details

Journal
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Published
2025-09-26
DOI
https://doi.org/10.1061/jladah.ladr-1390
Primary Topic
Image Processing and 3D Reconstruction
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Dispute Review Boards: Using the Law as a Guide in Settling Construction Contract Disputes

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Image Processing and 3D Reconstruction
article

Dispute Review Boards: Using the Law as a Guide in Settling Construction Contract Disputes

article en

Abstract

In the spring of 2017, a contractor submitted a Notice of Intent (NOI) to file a claim for additional compensation for implementation of “100% pile driving analysis (PDA)” on the production piles to achieve the required bearing capacity in Bents #5 and #6 of a bridge being constructed as part of a project to widen and improve a major thoroughfare in Pensacola, Florida. In the summer of that same year, the contractor submitted another NOI to file a separate claim for additional compensation for implementation of 100% PDA on the production piles in Bents #1, #2, and #3 of the same project. The contractor claimed that, based on geotechnical reports provided by Florida Department of Transportation, they (the contractor) did not expect to have to use the PDA, and thus did not bid the job to include the PDA; therefore, their having to employ the PDA was “unforeseeable work.” When the parties could not reach agreement, both parties requested a hearing be conducted by the Disputes Review Board (DRB) assigned to that project. The hearing focused on both claims. At the hearing’s conclusion, in a unanimous decision, the Board recommended “ENTITLEMENT” for the contractor. This paper offers insight into the progression of the DRB process from the beginning of the project to the conclusion of the hearing, as executed by one of the oldest and best-established DRB programs in the US.

Journal of Legal Affairs and Dispute Resolution in Engineering and ConstructionVol. 18(1)
University of Florida (US)
Openalex Percentile: Top 46%
Image Processing and 3D Reconstruction
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.