Integrated Project Delivery in Norway – the Clients’ Perspective on Challenges

The purpose of the paper is to identify and understand the clients’ motives for choosing Integrated Project Delivery (IPD) as a Project Delivery Model (PDM) and their experiences of the challenges in adopting it in Norway. This is an overlooked perspective as most studies focus on general benefits and barriers to IPD. The paper draws upon interviews with client representatives. The study reveals six recurring challenges across the projects: diverse motivations for choosing IPD, the necessity of enthusiasts to drive adoption, the challenge of convincing decision-makers that the public procurement regulations are not a showstopper, that agreeing on target prices can be hard and potentially lead to project collapse and that decision making within the IPD framework can be challenging. The findings show that the rationale for adopting IPD is based on a complex interplay of factors. We conclude by arguing that while enthusiasm is a powerful catalyst for IPD adoption, it must be balanced with rational decision making and a clear understanding of project-specific circumstances.

Publication Details

Journal
Annual Conference of the International Group for Lean Construction
Published
2025-06-02
DOI
https://doi.org/10.24928/2025/0154
Primary Topic
Geometric Analysis and Curvature Flows
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Integrated Project Delivery in Norway – the Clients’ Perspective on Challenges

Annual Conference of the International Group for Lean Construction
Geometric Analysis and Curvature Flows
article

Integrated Project Delivery in Norway – the Clients’ Perspective on Challenges

article en

Abstract

The purpose of the paper is to identify and understand the clients’ motives for choosing Integrated Project Delivery (IPD) as a Project Delivery Model (PDM) and their experiences of the challenges in adopting it in Norway. This is an overlooked perspective as most studies focus on general benefits and barriers to IPD. The paper draws upon interviews with client representatives. The study reveals six recurring challenges across the projects: diverse motivations for choosing IPD, the necessity of enthusiasts to drive adoption, the challenge of convincing decision-makers that the public procurement regulations are not a showstopper, that agreeing on target prices can be hard and potentially lead to project collapse and that decision making within the IPD framework can be challenging. The findings show that the rationale for adopting IPD is based on a complex interplay of factors. We conclude by arguing that while enthusiasm is a powerful catalyst for IPD adoption, it must be balanced with rational decision making and a clear understanding of project-specific circumstances.

Annual Conference of the International Group for Lean Construction
Peace, Justice and strong institutions
Openalex Percentile: Top 14%
Geometric Analysis and Curvature Flows
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Integrated Project Delivery in Norway – the Clients’ Perspective on Challenges · Annual Conference of the International Group for Lean Construction (2025) | TGRS Research Map | TGRS