EVALUASI PENGENDALIAN WAKTU DAN BIAYA PADA PROYEK KONSTRUKSI MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (STUDI KASUS : PEMBANGUNAN JEMBATAN AMPERA KECAMATAN BANJARANYAR KABUPATEN CIAMIS)

It is often found that projects experience delays in completion in their implementation in the field. Project control is indispensable because it affects the success of a project. The purpose of this study is to evaluate the control of time and cost in the Ampera Bridge Construction Project, Banjaranyar District, Ciamis Regency using the Earned Value Management method. This method analyzes time and cost deviations through Cost Variance and Schedule Variance. To assess the efficiency of resource use using the Cost Performance Index and Schedule Performance Index, and to analyze estimated costs and project completion times through ETC and EAC, as well as ETS and EAS. The results show that the schedule performance index value shows the average value of SPI >1, indicating that the project is running faster than the planned schedule, while the cost performance index CPI = 1 indicates the cost usage according to the budget. The project was successfully completed 100% 2 weeks ahead of schedule. The ETC value obtained in the 19th week is zero (0) which means that the cost budget has been exhausted and the work has been completed. The EAC value obtained is the same as the ACWP value, which is Rp 10,635,880,000.00 which shows that the project is running according to the cost plan and schedule. Although there are some delays in certain weeks, this case study shows that EVM is an effective method to control the time and cost of construction projects.

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-02-07
DOI
https://doi.org/10.25157/mediailmiahtekniksipil.v2i1.4096
Primary Topic
Vietnamese History and Culture Studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

EVALUASI PENGENDALIAN WAKTU DAN BIAYA PADA PROYEK KONSTRUKSI MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (STUDI KASUS : PEMBANGUNAN JEMBATAN AMPERA KECAMATAN BANJARANYAR KABUPATEN CIAMIS)

Jurnal Ilmiah Teknik Sipil
Vietnamese History and Culture Studies
article

EVALUASI PENGENDALIAN WAKTU DAN BIAYA PADA PROYEK KONSTRUKSI MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (STUDI KASUS : PEMBANGUNAN JEMBATAN AMPERA KECAMATAN BANJARANYAR KABUPATEN CIAMIS)

article en

Abstract

It is often found that projects experience delays in completion in their implementation in the field. Project control is indispensable because it affects the success of a project. The purpose of this study is to evaluate the control of time and cost in the Ampera Bridge Construction Project, Banjaranyar District, Ciamis Regency using the Earned Value Management method. This method analyzes time and cost deviations through Cost Variance and Schedule Variance. To assess the efficiency of resource use using the Cost Performance Index and Schedule Performance Index, and to analyze estimated costs and project completion times through ETC and EAC, as well as ETS and EAS. The results show that the schedule performance index value shows the average value of SPI >1, indicating that the project is running faster than the planned schedule, while the cost performance index CPI = 1 indicates the cost usage according to the budget. The project was successfully completed 100% 2 weeks ahead of schedule. The ETC value obtained in the 19th week is zero (0) which means that the cost budget has been exhausted and the work has been completed. The EAC value obtained is the same as the ACWP value, which is Rp 10,635,880,000.00 which shows that the project is running according to the cost plan and schedule. Although there are some delays in certain weeks, this case study shows that EVM is an effective method to control the time and cost of construction projects.

Jurnal Ilmiah Teknik SipilVol. 2(1)
Universitas Galuh (ID)
Decent work and economic growth
Openalex Percentile: Top 37%
Vietnamese History and Culture Studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.