Project Performance Evaluation Using Critical Path Method and Earned Value Management: A Comparative Analysis of Road Maintenance Projects in the 4th District of Camarines Sur

Road maintenance projects often face delays and budget overruns due to dispersed works, constrained time windows, and resource limitations. This study evaluates the comparative effectiveness of the Critical Path Method (CPM) and Earned Value Management (EVM), including Earned Schedule (ES), in monitoring the performance of road maintenance projects in the 4th District of Camarines Sur, Philippines. A descriptive–comparative design was applied, analyzing five purposively selected projects through documentary analysis, schedule reconstruction, EVM computation, and key informant validation. Findings reveal that CPM obtained a weighted mean rating of 4.3, emphasizing its strength in identifying critical activities and forecasting schedule delays, while EVM registered a mean of 4.4, highlighting its greater utility in cost efficiency and integrated performance analysis. Notably, the integrated CPM–EVM framework achieved the highest rating of 4.8, underscoring its superior usefulness and potential for institutional adoption in infrastructure project monitoring. The study recommends that the Department of Public Works and Highways (DPWH) institutionalize CPM–EVM integration to enhance accountability, early warning systems, and transparency in project delivery.

Institutions

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2025-09-09
DOI
https://doi.org/10.5281/zenodo.17085690
Primary Topic
Geochemistry and Geologic Mapping
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Project Performance Evaluation Using Critical Path Method and Earned Value Management: A Comparative Analysis of Road Maintenance Projects in the 4th District of Camarines Sur

Zenodo (CERN European Organization for Nuclear Research)
Geochemistry and Geologic Mapping
article

Project Performance Evaluation Using Critical Path Method and Earned Value Management: A Comparative Analysis of Road Maintenance Projects in the 4th District of Camarines Sur

article en

Abstract

Road maintenance projects often face delays and budget overruns due to dispersed works, constrained time windows, and resource limitations. This study evaluates the comparative effectiveness of the Critical Path Method (CPM) and Earned Value Management (EVM), including Earned Schedule (ES), in monitoring the performance of road maintenance projects in the 4th District of Camarines Sur, Philippines. A descriptive–comparative design was applied, analyzing five purposively selected projects through documentary analysis, schedule reconstruction, EVM computation, and key informant validation. Findings reveal that CPM obtained a weighted mean rating of 4.3, emphasizing its strength in identifying critical activities and forecasting schedule delays, while EVM registered a mean of 4.4, highlighting its greater utility in cost efficiency and integrated performance analysis. Notably, the integrated CPM–EVM framework achieved the highest rating of 4.8, underscoring its superior usefulness and potential for institutional adoption in infrastructure project monitoring. The study recommends that the Department of Public Works and Highways (DPWH) institutionalize CPM–EVM integration to enhance accountability, early warning systems, and transparency in project delivery.

Zenodo (CERN European Organization for Nuclear Research)
Partido State University (PH), Central Bicol State University of Agriculture (PH)
Industry, innovation and infrastructure
Openalex Percentile: Top 48%
Geochemistry and Geologic Mapping
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.