On the damping deterioration of power systems with CIG-based power plants performing PFR under communication delays

The primary frequency response of converter-interfaced generation power plants is a mandatory technical requirement of the grid connection codes. This is the case in Europe, where the grid code EU 2016/631 specifies mandatory frequency sensitive modes for power park modules of medium and high dimension. In this response, the active power output changes as a result of a frequency deviation in order to contribute to the restoration of the nominal frequency. The power plant controller that governs these type of plants is the responsible to perform this task. Plant-level control latency is primarily caused by communication delays, which increase the plant response time, thereby compromising the damping of network oscillation modes in the range of 0.1 to 1.5 Hz. The case presented here shows that in certain situations the primary frequency response, which is crucial for maintaining frequency stability, can seriously affect the oscillation damping of a power system. This can lead to so-called angle instability. Simulations show that PFR provision by PV plants can worsen damping when delays are present, especially with changes in system inertia or line length. • CIG PFR communication delays worsen the damping of power system oscillations. • The discrete-time model analyses the effects of PFR control latency on stability. • The impact of PFR delays on damping is sensitive to power system parameters.

Institutions

Publication Details

Journal
Electric Power Systems Research
Published
2025-08-27
DOI
https://doi.org/10.1016/j.epsr.2025.112077
Primary Topic
Geochemistry and Geologic Mapping
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

On the damping deterioration of power systems with CIG-based power plants performing PFR under communication delays

Electric Power Systems Research
Geochemistry and Geologic Mapping
article

On the damping deterioration of power systems with CIG-based power plants performing PFR under communication delays

article en

Abstract

The primary frequency response of converter-interfaced generation power plants is a mandatory technical requirement of the grid connection codes. This is the case in Europe, where the grid code EU 2016/631 specifies mandatory frequency sensitive modes for power park modules of medium and high dimension. In this response, the active power output changes as a result of a frequency deviation in order to contribute to the restoration of the nominal frequency. The power plant controller that governs these type of plants is the responsible to perform this task. Plant-level control latency is primarily caused by communication delays, which increase the plant response time, thereby compromising the damping of network oscillation modes in the range of 0.1 to 1.5 Hz. The case presented here shows that in certain situations the primary frequency response, which is crucial for maintaining frequency stability, can seriously affect the oscillation damping of a power system. This can lead to so-called angle instability. Simulations show that PFR provision by PV plants can worsen damping when delays are present, especially with changes in system inertia or line length. • CIG PFR communication delays worsen the damping of power system oscillations. • The discrete-time model analyses the effects of PFR control latency on stability. • The impact of PFR delays on damping is sensitive to power system parameters.

Electric Power Systems ResearchVol. 250
University of Belgrade (RS), Universidad de Sevilla (ES)
Affordable and clean energy
Openalex Percentile: Top 65%
Geochemistry and Geologic Mapping
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.