Predictive Modeling for Cost and Duration Estimation in Residential Construction Projects Using Machine Learning Algorithms

This study explores the application of machine learning algorithms in predicting cost and duration ofstandard residential projects. The researchers considered eight (8) parameters, and these are gathered fromdifferent construction companies in Pampanga. A total of 60 projects were gathered. Using the mostoptimal data splitting method, 42 of these projects were used for training the predictive model, and 18were used for testing. Python and visual studio code were used in creating the predictive model. Pearson ofcorrelation coefficient (r) was used to measure the correlation of the variables. Six (6) resulted to havestrong positive correlation. The other two (2) were categorized as moderate positive correlation. The Rsquared values of the regression models were tested to acquire the most optimal model. The Ridgeregression model resulted in the highest r squared value of 0.81. To test the accuracy of the forecastedresults, mean absolute percentage error (MAPE) was used. A MAPE value of 7.20 was obtained from thecost model, and 6.21 for duration model. These MAPE values indicate that the predictive model isconsidered “highly accurate forecasting”.

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2025-08-22
DOI
https://doi.org/10.5281/zenodo.16926833
Primary Topic
Geochemistry and Geologic Mapping
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Predictive Modeling for Cost and Duration Estimation in Residential Construction Projects Using Machine Learning Algorithms

Zenodo (CERN European Organization for Nuclear Research)
Geochemistry and Geologic Mapping
article

Predictive Modeling for Cost and Duration Estimation in Residential Construction Projects Using Machine Learning Algorithms

article en

Abstract

This study explores the application of machine learning algorithms in predicting cost and duration ofstandard residential projects. The researchers considered eight (8) parameters, and these are gathered fromdifferent construction companies in Pampanga. A total of 60 projects were gathered. Using the mostoptimal data splitting method, 42 of these projects were used for training the predictive model, and 18were used for testing. Python and visual studio code were used in creating the predictive model. Pearson ofcorrelation coefficient (r) was used to measure the correlation of the variables. Six (6) resulted to havestrong positive correlation. The other two (2) were categorized as moderate positive correlation. The Rsquared values of the regression models were tested to acquire the most optimal model. The Ridgeregression model resulted in the highest r squared value of 0.81. To test the accuracy of the forecastedresults, mean absolute percentage error (MAPE) was used. A MAPE value of 7.20 was obtained from thecost model, and 6.21 for duration model. These MAPE values indicate that the predictive model isconsidered “highly accurate forecasting”.

Zenodo (CERN European Organization for Nuclear Research)
Sustainable cities and communities
Openalex Percentile: Top 68%
Geochemistry and Geologic Mapping
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Predictive Modeling for Cost and Duration Estimation in Residential Construction Projects Using Machine Learning Algorithms · Zenodo (CERN European Organization for Nuclear Research) (2025) | TGRS Research Map | TGRS