Розробка моделі аналізу витрат на непередбачені випадки в будівельному проекті з інтеграцією ризиків витрат, часу та якості

The object of this study is the contingency cost in the implementation of construction projects. The problem to be solved is the develop a contingency cost model in the implementation of construction projects, by integrating cost, quality, and time risks. The previously used models involve cost, quality, and time risks separately. It is still rare to find an analysis in construction project execution that incorporates these three risks into a contingency cost model. The formulation of this integration is crucial since every project is unique and carries varying degrees of risk. Data were investigated and collected from the Bali Province Regency Road Improvement Project, and the descriptive strategy analysis was employed. Using the probability (P) by impact (I) approach, which is the multiplication of (P) by (I) on a Likert scale of 5, triple constraint risks are included in the Expected Monetary Value (EMV) analysis. Moreover, monetary units are used to develop impact scale I, in which daily penalties and quality with rework costs are applied using the monetary unit approach of time effect. The simultaneous total of the PI from time, cost, and quality concerns is the EMV contingency cost formulation for the integration of these risks. The study obtained that, a cost contingency model was created that incorporates the risk factors of cost, time, and quality. This model’s cost contingency value was 9.61% of the total cost when it was applied to a case study. Specifically, this finding falls between 5% and 10%, which is adequate and consistent with the empirical approach. This contingency cost model is thought to be more rational since it accounts for project risks, including the likelihood of potential risks as well as their effects. The project team can use this approach to estimate contingency expenses

Publication Details

Journal
Scientific periodicals of Ukraine
Published
2025-06-30
Primary Topic
Laser Design and Applications
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Розробка моделі аналізу витрат на непередбачені випадки в будівельному проекті з інтеграцією ризиків витрат, часу та якості

Scientific periodicals of Ukraine
Laser Design and Applications
article

Розробка моделі аналізу витрат на непередбачені випадки в будівельному проекті з інтеграцією ризиків витрат, часу та якості

article en

Abstract

The object of this study is the contingency cost in the implementation of construction projects. The problem to be solved is the develop a contingency cost model in the implementation of construction projects, by integrating cost, quality, and time risks. The previously used models involve cost, quality, and time risks separately. It is still rare to find an analysis in construction project execution that incorporates these three risks into a contingency cost model. The formulation of this integration is crucial since every project is unique and carries varying degrees of risk. Data were investigated and collected from the Bali Province Regency Road Improvement Project, and the descriptive strategy analysis was employed. Using the probability (P) by impact (I) approach, which is the multiplication of (P) by (I) on a Likert scale of 5, triple constraint risks are included in the Expected Monetary Value (EMV) analysis. Moreover, monetary units are used to develop impact scale I, in which daily penalties and quality with rework costs are applied using the monetary unit approach of time effect. The simultaneous total of the PI from time, cost, and quality concerns is the EMV contingency cost formulation for the integration of these risks. The study obtained that, a cost contingency model was created that incorporates the risk factors of cost, time, and quality. This model’s cost contingency value was 9.61% of the total cost when it was applied to a case study. Specifically, this finding falls between 5% and 10%, which is adequate and consistent with the empirical approach. This contingency cost model is thought to be more rational since it accounts for project risks, including the likelihood of potential risks as well as their effects. The project team can use this approach to estimate contingency expenses

Scientific periodicals of Ukraine
Openalex Percentile: Top 51%
Laser Design and Applications
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.