Predictive Scheduling for Repetitive Construction: A Machine Learning Framework for Enhanced Resource and Time Management

Repetitive construction projects, characterized by the sequential execution of similar tasks across multiple units, present unique scheduling challenges, particularly concerning resource crew continuity and overall project duration. Traditional scheduling methods often fall short in optimizing these dual objectives simultaneously. This paper proposes a novel framework that integrates machine learning (ML) algorithms with established repetitive project scheduling principles to achieve enhanced optimal scheduling. Various ML models are applied to predict optimal crew allocation strategies and forecast potential work breaks or delays, thereby informing dynamic scheduling adjustments. The methodology aims to balance the minimization of project duration with the maximization of crew work continuity, a critical factor for productivity and cost efficiency. Through a comprehensive evaluation of ML model performance metrics, we demonstrate the efficacy of this data-driven approach in providing predictive insights and decision support for project managers. The findings highlight the transformative potential of machine learning in revolutionizing repetitive construction project scheduling, leading to more efficient resource utilization, reduced project risks, and improved overall project performance.

Institutions

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2024-12-31
DOI
https://doi.org/10.5281/zenodo.14468749
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Predictive Scheduling for Repetitive Construction: A Machine Learning Framework for Enhanced Resource and Time Management

Zenodo (CERN European Organization for Nuclear Research)
Resource-Constrained Project Scheduling
article

Predictive Scheduling for Repetitive Construction: A Machine Learning Framework for Enhanced Resource and Time Management

article en

Abstract

Repetitive construction projects, characterized by the sequential execution of similar tasks across multiple units, present unique scheduling challenges, particularly concerning resource crew continuity and overall project duration. Traditional scheduling methods often fall short in optimizing these dual objectives simultaneously. This paper proposes a novel framework that integrates machine learning (ML) algorithms with established repetitive project scheduling principles to achieve enhanced optimal scheduling. Various ML models are applied to predict optimal crew allocation strategies and forecast potential work breaks or delays, thereby informing dynamic scheduling adjustments. The methodology aims to balance the minimization of project duration with the maximization of crew work continuity, a critical factor for productivity and cost efficiency. Through a comprehensive evaluation of ML model performance metrics, we demonstrate the efficacy of this data-driven approach in providing predictive insights and decision support for project managers. The findings highlight the transformative potential of machine learning in revolutionizing repetitive construction project scheduling, leading to more efficient resource utilization, reduced project risks, and improved overall project performance.

Zenodo (CERN European Organization for Nuclear Research)
National Institute of Construction Management and Research (IN)
Decent work and economic growth
Openalex Percentile: Top 45%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.