Analysis of factors affecting Efficient Practices and Techniques for Allocating Provisional Sums in Construction Management

Cost estimation for electrical services in construction projects remains a critical challenge, particularly in Nigeria, where cost uncertainties in mechanical and electrical (M&E) services lead to budget overruns and project delays. The estimation of provisional sums for electrical installations is often imprecise due to incomplete design specifications, fluctuating market prices, and the absence of standardized estimation frameworks. These limitations impact financial planning, contractor-client relationships, and overall project efficiency. This study aims to analyse effective cost estimation techniques for allocating provisional sums in electrical installations and to identify causal factors affecting their accuracy. Specifically, it seeks to examine current industry practices, analyze the reliability of various estimating techniques, and propose a refined framework for improving cost estimation accuracy in electrical services. A quantitative research design was adopted, utilizing structured questionnaires administered to 83 professionals, including quantity surveyors, electrical engineers, and project managers involved in residential construction projects in Owerri, Nigeria. Simple random and snowball sampling methods were used to ensure a representative sample of experienced professionals. The collected data were analyzed using descriptive statistics. The findings highlight that engineering cost estimating and resource analysis emerged as the most effective methodologies for determining provisional sums. However, factors such as incomplete design details, unclear specifications, and organizational policies significantly impact the accuracy of estimates. The study concludes that improving the proficiency of estimators, integrating modern computational tools, and ensuring complete project specifications can significantly enhance cost estimation accuracy. It recommends the adoption of digital modeling techniques, increased training for cost estimators, and the establishment of standardized guidelines for electrical service cost estimation. These improvements can help mitigate cost-related disputes, optimize budget allocations, and improve overall project outcomes.

Institutions

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2025-03-06
DOI
https://doi.org/10.5281/zenodo.14981461
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of factors affecting Efficient Practices and Techniques for Allocating Provisional Sums in Construction Management

Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
article

Analysis of factors affecting Efficient Practices and Techniques for Allocating Provisional Sums in Construction Management

article en

Abstract

Cost estimation for electrical services in construction projects remains a critical challenge, particularly in Nigeria, where cost uncertainties in mechanical and electrical (M&E) services lead to budget overruns and project delays. The estimation of provisional sums for electrical installations is often imprecise due to incomplete design specifications, fluctuating market prices, and the absence of standardized estimation frameworks. These limitations impact financial planning, contractor-client relationships, and overall project efficiency. This study aims to analyse effective cost estimation techniques for allocating provisional sums in electrical installations and to identify causal factors affecting their accuracy. Specifically, it seeks to examine current industry practices, analyze the reliability of various estimating techniques, and propose a refined framework for improving cost estimation accuracy in electrical services. A quantitative research design was adopted, utilizing structured questionnaires administered to 83 professionals, including quantity surveyors, electrical engineers, and project managers involved in residential construction projects in Owerri, Nigeria. Simple random and snowball sampling methods were used to ensure a representative sample of experienced professionals. The collected data were analyzed using descriptive statistics. The findings highlight that engineering cost estimating and resource analysis emerged as the most effective methodologies for determining provisional sums. However, factors such as incomplete design details, unclear specifications, and organizational policies significantly impact the accuracy of estimates. The study concludes that improving the proficiency of estimators, integrating modern computational tools, and ensuring complete project specifications can significantly enhance cost estimation accuracy. It recommends the adoption of digital modeling techniques, increased training for cost estimators, and the establishment of standardized guidelines for electrical service cost estimation. These improvements can help mitigate cost-related disputes, optimize budget allocations, and improve overall project outcomes.

Zenodo (CERN European Organization for Nuclear Research)
Nnamdi Azikiwe University (NG)
Industry, innovation and infrastructure
Openalex Percentile: Top 44%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Analysis of factors affecting Efficient Practices and Techniques for Allocating Provisional Sums in Construction Management · Zenodo (CERN European Organization for Nuclear Research) (2025) | TGRS Research Map | TGRS