Risk Prevention-control and Structural Safety Analysis of Multi-line Tunnel Parallel Construction in Sandstone Strata

[Objective]During the parallel construction of multi-line tunnels, the excavation of subsequent tunnels will adversely disturb existing tunnels. Compared to double-line tunnels, the disturbance caused by multi-line tunnel parallel construction is more complex, necessitating researches on risk prevention-control strategies and structural safety. [Method]Using a rail transit interval line and depot station underground excavation tunnel project as example, risk identification, prevention-control and safety analysis are conducted. The structural reliability criteria are used to quantify and determine highly affected areas during three-line tunnel parallel construction. The risk prevention-control measures for existing underground excavation tunnels in these highly affected areas, specifically in-tunnel reinforcement measures are introduced. A three-dimensional refined numerical model is established, the land subsidence and existing tunnel stressed deformation corresponding to different stages of tunnel parallel construction are analyzed, and the structural safety states and reliability of reinforced measures are evaluated. [Result & Conclusion]Existing underground excavation tunnels with small clearance exhibit significant displacement and deformation during the excavation of the right-line shield tunnel. The disturbance impact caused by the subsequent shield tunnel decreases significantly as the distance from the preceding tunnel increases. The overall reinforcement measures using cross braces and arch canopies can effectively mitigate the additional deformation and stress on existing structures caused by the disturbance of subsequent shield tunnel construction.

Institutions

Publication Details

Journal
SHILAP Revista de lepidopterología
Published
2024-12-01
DOI
https://doi.org/10.16037/j.1007-869x.2024.12.006
Primary Topic
Civil and Geotechnical Engineering Research
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Risk Prevention-control and Structural Safety Analysis of Multi-line Tunnel Parallel Construction in Sandstone Strata

SHILAP Revista de lepidopterología
Civil and Geotechnical Engineering Research
article

Risk Prevention-control and Structural Safety Analysis of Multi-line Tunnel Parallel Construction in Sandstone Strata

article en

Abstract

[Objective]During the parallel construction of multi-line tunnels, the excavation of subsequent tunnels will adversely disturb existing tunnels. Compared to double-line tunnels, the disturbance caused by multi-line tunnel parallel construction is more complex, necessitating researches on risk prevention-control strategies and structural safety. [Method]Using a rail transit interval line and depot station underground excavation tunnel project as example, risk identification, prevention-control and safety analysis are conducted. The structural reliability criteria are used to quantify and determine highly affected areas during three-line tunnel parallel construction. The risk prevention-control measures for existing underground excavation tunnels in these highly affected areas, specifically in-tunnel reinforcement measures are introduced. A three-dimensional refined numerical model is established, the land subsidence and existing tunnel stressed deformation corresponding to different stages of tunnel parallel construction are analyzed, and the structural safety states and reliability of reinforced measures are evaluated. [Result & Conclusion]Existing underground excavation tunnels with small clearance exhibit significant displacement and deformation during the excavation of the right-line shield tunnel. The disturbance impact caused by the subsequent shield tunnel decreases significantly as the distance from the preceding tunnel increases. The overall reinforcement measures using cross braces and arch canopies can effectively mitigate the additional deformation and stress on existing structures caused by the disturbance of subsequent shield tunnel construction.

SHILAP Revista de lepidopterología
China Railway Fifth Survey and Design Institute Group (CN)
Sustainable cities and communities
Openalex Percentile: Top 32%
Civil and Geotechnical Engineering Research
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.