Railway Bridges over Dunav-Tisa-Dunav (DTD) Channel as part of the High-Speed Railway Design Belgrade-Budapest, Section Novi Sad-Subotica-State Border

As part of the design of the Belgrade-Budapest high-speed railway project, the design of the section Novi Sad-Subotica-State border with a length of 108 km was completed. The railway is designed for a maximum speed up to 200 km/h. The route of the Novi Sad - Subotica - State border high-speed railway crosses the Danube-Tisa-Danube canal (DTD) in several places. The most significant bridges over the canal are: 1. The bridge at km 81+644 is a continuous steel truss bridge on three spans of 42.0+56.0+56.0 m. 2. The bridge at km 0+796 is a continuous girder on three spans of 27.6+82.8+27.6 m. The end span sections are box girders, while the middle span is designed as a steel truss. 3. The bridge at km 110+351 is a simply supported beam, steel truss bridge with a span of 63.0 m. 4. The bridge at km 117+151 with a total length of 1463 m is the longest bridge on the alignment. There are a total of 43 piers. Majority of structures are prestressed concrete beams L=31.5 m, box girder section. 8 spans are steel trusses of span L=48.75 m. The designs of all structures were done according to Eurocode, UIC and RIL recommendations. The Design for Building Permit was completed during 2021, the Design for Construction (DFC) [1] in the first half of 2022. The works started in July 2022 and new line opening is expected by the end of 2024.

Publication Details

Journal
mediaTUM (Technical University of Munich)
Published
2024-11-20
DOI
https://doi.org/10.14459/icbdb24.24
Primary Topic
Structural Engineering and Vibration Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Railway Bridges over Dunav-Tisa-Dunav (DTD) Channel as part of the High-Speed Railway Design Belgrade-Budapest, Section Novi Sad-Subotica-State Border

mediaTUM (Technical University of Munich)
Structural Engineering and Vibration Analysis
article

Railway Bridges over Dunav-Tisa-Dunav (DTD) Channel as part of the High-Speed Railway Design Belgrade-Budapest, Section Novi Sad-Subotica-State Border

article en

Abstract

As part of the design of the Belgrade-Budapest high-speed railway project, the design of the section Novi Sad-Subotica-State border with a length of 108 km was completed. The railway is designed for a maximum speed up to 200 km/h. The route of the Novi Sad - Subotica - State border high-speed railway crosses the Danube-Tisa-Danube canal (DTD) in several places. The most significant bridges over the canal are: 1. The bridge at km 81+644 is a continuous steel truss bridge on three spans of 42.0+56.0+56.0 m. 2. The bridge at km 0+796 is a continuous girder on three spans of 27.6+82.8+27.6 m. The end span sections are box girders, while the middle span is designed as a steel truss. 3. The bridge at km 110+351 is a simply supported beam, steel truss bridge with a span of 63.0 m. 4. The bridge at km 117+151 with a total length of 1463 m is the longest bridge on the alignment. There are a total of 43 piers. Majority of structures are prestressed concrete beams L=31.5 m, box girder section. 8 spans are steel trusses of span L=48.75 m. The designs of all structures were done according to Eurocode, UIC and RIL recommendations. The Design for Building Permit was completed during 2021, the Design for Construction (DFC) [1] in the first half of 2022. The works started in July 2022 and new line opening is expected by the end of 2024.

mediaTUM (Technical University of Munich)
Sustainable cities and communities
Openalex Percentile: Top 60%
Structural Engineering and Vibration Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Railway Bridges over Dunav-Tisa-Dunav (DTD) Channel as part of the High-Speed Railway Design Belgrade-Budapest, Section Novi Sad-Subotica-State Border · mediaTUM (Technical University of Munich) (2024) | TGRS Research Map | TGRS