Forecasting Delays and Budget overruns resulting from Material-Related Factors

The construction industry's success hinges on effective materials management, a complex process vital for timely and cost-effective material availability. Despite its significance, a notable gap exists in academic research on this critical aspect. This study addresses the gap by introducing a delay prediction model aimed at preempting project delays due to material-related challenges, offering a proactive project management strategy. Materials account for 60-70% of direct costs, and delays resulting from inefficiencies incur significant financial implications. The proposed algorithm, rooted in rigorous academic exploration, utilizes correlation matrices to predict time and cost overruns. The research concludes with a comprehensive analysis, validating the algorithm's utility by revealing average delays and cost overruns for diverse construction components. This study underscores the paramount importance of materials management in construction project success and offers a practical algorithm with potential real-time applications, suggesting avenues for future research expansion.

Publication Details

Journal
Springer Link (Chiba Institute of Technology)
Published
2024-08-30
DOI
https://doi.org/10.1051/e3sconf/202456302045/pdf
Primary Topic
Mycorrhizal Fungi and Plant Interactions
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Forecasting Delays and Budget overruns resulting from Material-Related Factors

Springer Link (Chiba Institute of Technology)
Mycorrhizal Fungi and Plant Interactions
article

Forecasting Delays and Budget overruns resulting from Material-Related Factors

article en

Abstract

The construction industry's success hinges on effective materials management, a complex process vital for timely and cost-effective material availability. Despite its significance, a notable gap exists in academic research on this critical aspect. This study addresses the gap by introducing a delay prediction model aimed at preempting project delays due to material-related challenges, offering a proactive project management strategy. Materials account for 60-70% of direct costs, and delays resulting from inefficiencies incur significant financial implications. The proposed algorithm, rooted in rigorous academic exploration, utilizes correlation matrices to predict time and cost overruns. The research concludes with a comprehensive analysis, validating the algorithm's utility by revealing average delays and cost overruns for diverse construction components. This study underscores the paramount importance of materials management in construction project success and offers a practical algorithm with potential real-time applications, suggesting avenues for future research expansion.

Springer Link (Chiba Institute of Technology)
Industry, innovation and infrastructure
Openalex Percentile: Top 53%
Mycorrhizal Fungi and Plant Interactions
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Forecasting Delays and Budget overruns resulting from Material-Related Factors · Springer Link (Chiba Institute of Technology) (2024) | TGRS Research Map | TGRS