Assessment of Groundwater Potential as Alternative Water Resource for Kapar Power Plants

The current surface water shortage due to drought is prompting industries in Peninsular Malaysia to explore alternative water resources (AWR). Tenaga Nasional Berhad (TNB)’s reliance on town water has increased the risk of interruptions in supply, exposing the plant to shutdowns and reduced generation capacity. Consequently, TNB requires alternative water sources to mitigate these risks. This study aims to assess the groundwater potential at the Kapar Power Plant in terms of volume and quality as an alternative resource. Hydrogeological and geophysical surveys were conducted to locate prospective groundwater and determine its characteristics. Specifically, 2-D Electrical Resistivity Imaging (ERI) and Induced Polarization (IP) surveys were carried out using the ABEM Terrameter SAS 4000 and the ES10-64 electrode selector. A total of five survey lines were established, revealing four potential groundwater locations. However, two locations were selected for further evaluation, with a total yield of 15.5 m³/hr. This study provides valuable insights into utilizing groundwater as a sustainable alternative water source for TNB, helping to ensure operational stability and reliability for the power plant.

Publication Details

Journal
Springer Link (Chiba Institute of Technology)
Published
2024-10-15
DOI
https://doi.org/10.1051/bioconf/202413104013/pdf
Primary Topic
Geophysical and Geoelectrical Methods
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Assessment of Groundwater Potential as Alternative Water Resource for Kapar Power Plants

Springer Link (Chiba Institute of Technology)
Geophysical and Geoelectrical Methods
article

Assessment of Groundwater Potential as Alternative Water Resource for Kapar Power Plants

article en

Abstract

The current surface water shortage due to drought is prompting industries in Peninsular Malaysia to explore alternative water resources (AWR). Tenaga Nasional Berhad (TNB)’s reliance on town water has increased the risk of interruptions in supply, exposing the plant to shutdowns and reduced generation capacity. Consequently, TNB requires alternative water sources to mitigate these risks. This study aims to assess the groundwater potential at the Kapar Power Plant in terms of volume and quality as an alternative resource. Hydrogeological and geophysical surveys were conducted to locate prospective groundwater and determine its characteristics. Specifically, 2-D Electrical Resistivity Imaging (ERI) and Induced Polarization (IP) surveys were carried out using the ABEM Terrameter SAS 4000 and the ES10-64 electrode selector. A total of five survey lines were established, revealing four potential groundwater locations. However, two locations were selected for further evaluation, with a total yield of 15.5 m³/hr. This study provides valuable insights into utilizing groundwater as a sustainable alternative water source for TNB, helping to ensure operational stability and reliability for the power plant.

Springer Link (Chiba Institute of Technology)
Openalex Percentile: Top 63%
Geophysical and Geoelectrical Methods
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Assessment of Groundwater Potential as Alternative Water Resource for Kapar Power Plants · Springer Link (Chiba Institute of Technology) (2024) | TGRS Research Map | TGRS