LT-bridge Construction Method for the Material-saving and Fast Construction of Post-tensioned Concrete Bridges

Owners of bridges in the Danube Basin will face enormous challenges in the coming years because many bridges need to be renovated or rebuilt. They can either not withstand the current loads or have developed durability problems. Discussions with owners have shown that rapid construction progress is crucial for bridge replacements. The construction sites should disrupt the normal traffic flow as little as possible. As a result, a new, resource-saving, and fast construction method for bridges has been developed at TU Wien. Innovative prefabricated elements for the longitudinal girders and the deck slab were designed to fulfill these requirements. The prefabricated elements are connected by reinforcement and an in-situ concrete layer at the construction site. A comparison of the environmental impact based on the construction materials (life cycle phases A1–A3) between a construction section of an LT-bridge and a typical German motorway bridge shows a much lower global warming potential for the new bridge construction method due to the savings in construction materials in comparison to a conventional post-tensioned concrete bridge with in-situ concrete.

Publication Details

Journal
mediaTUM (Technical University of Munich)
Published
2024-11-20
DOI
https://doi.org/10.14459/icbdb24.38
Primary Topic
Civil and Structural Engineering Research
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

LT-bridge Construction Method for the Material-saving and Fast Construction of Post-tensioned Concrete Bridges

mediaTUM (Technical University of Munich)
Civil and Structural Engineering Research
article

LT-bridge Construction Method for the Material-saving and Fast Construction of Post-tensioned Concrete Bridges

article en

Abstract

Owners of bridges in the Danube Basin will face enormous challenges in the coming years because many bridges need to be renovated or rebuilt. They can either not withstand the current loads or have developed durability problems. Discussions with owners have shown that rapid construction progress is crucial for bridge replacements. The construction sites should disrupt the normal traffic flow as little as possible. As a result, a new, resource-saving, and fast construction method for bridges has been developed at TU Wien. Innovative prefabricated elements for the longitudinal girders and the deck slab were designed to fulfill these requirements. The prefabricated elements are connected by reinforcement and an in-situ concrete layer at the construction site. A comparison of the environmental impact based on the construction materials (life cycle phases A1–A3) between a construction section of an LT-bridge and a typical German motorway bridge shows a much lower global warming potential for the new bridge construction method due to the savings in construction materials in comparison to a conventional post-tensioned concrete bridge with in-situ concrete.

mediaTUM (Technical University of Munich)
Responsible consumption and production
Openalex Percentile: Top 63%
Civil and Structural Engineering Research
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

LT-bridge Construction Method for the Material-saving and Fast Construction of Post-tensioned Concrete Bridges · mediaTUM (Technical University of Munich) (2024) | TGRS Research Map | TGRS