Optimizing Time and Cost Efficiency in Delayed Construction Project Using Project Crashing Approach (A Case Study of a Geothermal Power Plant Operator in Indonesia)

Abstract : Electricity is a fundamental need that supports modern life across household, industries, and public sector. To ensure the sustainability of electricity in Java and Bali, PT GSE,a Geothermal Power Plant in Pengalengan, West Java, conduct a base structure replacement project for cooling tower which innitialy using the wooden base structure into the Fibre Reinforced Polymer (FRP). This project, known as Project X, was executed by PT XYZ as the EPC contractor. During the execution, cooling tower unit – 1 faced significant delay, posing financial and reputational risks. This research aims to identify the root causes of the delay, evaluate the losses, and proposed solutions for time and cost efficiency using the project crashing method. This research combine interview with key personnel and secondary company data. The critical path analysis conducted by using the Activity on Node (AON) approach, activity mapping using Precedence Diagram Method (PDM), and calculation for additional cost due to overtime conducted by using minimum wages (UMK) for Kabupaten Bandung in 2025. S Curve analysis shows 10 weeks of delay, mainly due to frequent bad weather that prevented outdoor activities according to the HSSE policies. Financially, if there is no corrective action to handle the delay, PT XYZ would be subjected to a project penalty of Rp 2.734.770.052, as stipulated in the cooperation contract with PT GSE. To anticipate the losses, the proposed solution is project crashing by conducting overtime to the critical path activites, which is safer dan more efficient comparing to adding new additional resources. The implementation of project crashing calculated need extra funding about Rp 399.544.839 which only 14,61% compared to the potential penalty sanction. Beyond the financial impact, this strategy also maintains client trust and strengthen future business opportunities.

Institutions

Publication Details

Journal
Zenodo (CERN European Organization for Nuclear Research)
Published
2025-05-05
DOI
https://doi.org/10.5281/zenodo.15340386
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Optimizing Time and Cost Efficiency in Delayed Construction Project Using Project Crashing Approach (A Case Study of a Geothermal Power Plant Operator in Indonesia)

Zenodo (CERN European Organization for Nuclear Research)
Construction Project Management and Performance
article

Optimizing Time and Cost Efficiency in Delayed Construction Project Using Project Crashing Approach (A Case Study of a Geothermal Power Plant Operator in Indonesia)

article en

Abstract

Abstract : Electricity is a fundamental need that supports modern life across household, industries, and public sector. To ensure the sustainability of electricity in Java and Bali, PT GSE,a Geothermal Power Plant in Pengalengan, West Java, conduct a base structure replacement project for cooling tower which innitialy using the wooden base structure into the Fibre Reinforced Polymer (FRP). This project, known as Project X, was executed by PT XYZ as the EPC contractor. During the execution, cooling tower unit – 1 faced significant delay, posing financial and reputational risks. This research aims to identify the root causes of the delay, evaluate the losses, and proposed solutions for time and cost efficiency using the project crashing method. This research combine interview with key personnel and secondary company data. The critical path analysis conducted by using the Activity on Node (AON) approach, activity mapping using Precedence Diagram Method (PDM), and calculation for additional cost due to overtime conducted by using minimum wages (UMK) for Kabupaten Bandung in 2025. S Curve analysis shows 10 weeks of delay, mainly due to frequent bad weather that prevented outdoor activities according to the HSSE policies. Financially, if there is no corrective action to handle the delay, PT XYZ would be subjected to a project penalty of Rp 2.734.770.052, as stipulated in the cooperation contract with PT GSE. To anticipate the losses, the proposed solution is project crashing by conducting overtime to the critical path activites, which is safer dan more efficient comparing to adding new additional resources. The implementation of project crashing calculated need extra funding about Rp 399.544.839 which only 14,61% compared to the potential penalty sanction. Beyond the financial impact, this strategy also maintains client trust and strengthen future business opportunities.

Zenodo (CERN European Organization for Nuclear Research)
Bandung Institute of Technology (ID)
Industry, innovation and infrastructure
Openalex Percentile: Top 52%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Optimizing Time and Cost Efficiency in Delayed Construction Project Using Project Crashing Approach (A Case Study of a Geothermal Power Plant Operator in Indonesia) · Zenodo (CERN European Organization for Nuclear Research) (2025) | TGRS Research Map | TGRS