Critical Risk Factors Affecting Time and Cost in Highway Construction: A Global Systematic Literature Review

This study presents a systematic literature review of critical risk factors affecting the time and cost performance of highway construction projects. Drawing from 83 peer-reviewed studies across multiple geographic regions, the paper identifies recurrent drivers of project delay and cost overrun in highway construction. The most frequently reported risks include (1) financial constraints, (2) political regulatory issues; (3) land-acquisition and right-of-way delays; (4) design and scope changes; (5) utilities relocation/conflicts; (6) materials and equipment shortages; (7) contractor-related issues; (8) planning and scheduling weaknesses; (9) labour and personnel issues; and (10) weather conditions. These risk factors collectively highlight the importance of robust planning, proactive stakeholder coordination, and the integration of risk-informed decision-making tools. The findings emphasize the need for targeted risk mitigation during early project stages and provide a foundation for refining risk assessment frameworks and future research directions in transport infrastructure development.

Authors

Institutions

Publication Details

Journal
Future Transportation
Published
2025-12-05
DOI
https://doi.org/10.3390/futuretransp5040192
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Critical Risk Factors Affecting Time and Cost in Highway Construction: A Global Systematic Literature Review

Harry Evdorides, Richard J. Davies, Aigul Zhasmukhambetova
Future Transportation
Construction Project Management and Performance
article

Critical Risk Factors Affecting Time and Cost in Highway Construction: A Global Systematic Literature Review

Harry Evdorides, Richard J. Davies, Aigul Zhasmukhambetova
article en

Abstract

This study presents a systematic literature review of critical risk factors affecting the time and cost performance of highway construction projects. Drawing from 83 peer-reviewed studies across multiple geographic regions, the paper identifies recurrent drivers of project delay and cost overrun in highway construction. The most frequently reported risks include (1) financial constraints, (2) political regulatory issues; (3) land-acquisition and right-of-way delays; (4) design and scope changes; (5) utilities relocation/conflicts; (6) materials and equipment shortages; (7) contractor-related issues; (8) planning and scheduling weaknesses; (9) labour and personnel issues; and (10) weather conditions. These risk factors collectively highlight the importance of robust planning, proactive stakeholder coordination, and the integration of risk-informed decision-making tools. The findings emphasize the need for targeted risk mitigation during early project stages and provide a foundation for refining risk assessment frameworks and future research directions in transport infrastructure development.

Future TransportationVol. 5(4)
University of Birmingham (GB)
Openalex Percentile: Top 56%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Critical Risk Factors Affecting Time and Cost in Highway Construction: A Global Systematic Literature Review — Harry Evdorides, Richard J. Davies, et al. · Future Transportation (2025) | TGRS Research Map | TGRS