Time–cost combined optimization in planning infrastructure construction projects under environment induced time‐window constraints

To accommodate environment-induced time-window constraints, environment-sensitive activities are arranged within allowable time windows while maintaining technological precedence and other logical relationships on the project. This research advances classical time–cost trade-off (TCT) analysis by incorporating time-window constraints in project planning, creating a more complex optimization problem that becomes computationally prohibitive for real-world applications. To overcome this challenge, an integrated project planning framework combining project time and cost into a single objective function is formalized. The optimization solution employs time-window scheduling algorithms to simulate method combinations through enumerated simulation. A reward function is defined to evaluate alternatives based on their impact on project cost and duration. In addition, a sample size reduction technique is utilized to maintain computational efficiency of random sampling without sacrificing accuracy. The methodology's practical application is demonstrated through a case study of a river-crossing bridge project in remote northern Canada, which is planned to validate its effectiveness in planning real-world infrastructure projects under stringent environment-induced time-window constraints.

Authors

Institutions

Publication Details

Journal
Computer-Aided Civil and Infrastructure Engineering
Published
2025-12-01
DOI
https://doi.org/10.1111/mice.70175
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Time–cost combined optimization in planning infrastructure construction projects under environment induced time‐window constraints

Serhii Naumets, Ming Lu, Kai Qi
Computer-Aided Civil and Infrastructure Engineering
Resource-Constrained Project Scheduling
article

Time–cost combined optimization in planning infrastructure construction projects under environment induced time‐window constraints

Serhii Naumets, Ming Lu, Kai Qi
article en

Abstract

To accommodate environment-induced time-window constraints, environment-sensitive activities are arranged within allowable time windows while maintaining technological precedence and other logical relationships on the project. This research advances classical time–cost trade-off (TCT) analysis by incorporating time-window constraints in project planning, creating a more complex optimization problem that becomes computationally prohibitive for real-world applications. To overcome this challenge, an integrated project planning framework combining project time and cost into a single objective function is formalized. The optimization solution employs time-window scheduling algorithms to simulate method combinations through enumerated simulation. A reward function is defined to evaluate alternatives based on their impact on project cost and duration. In addition, a sample size reduction technique is utilized to maintain computational efficiency of random sampling without sacrificing accuracy. The methodology's practical application is demonstrated through a case study of a river-crossing bridge project in remote northern Canada, which is planned to validate its effectiveness in planning real-world infrastructure projects under stringent environment-induced time-window constraints.

Computer-Aided Civil and Infrastructure EngineeringVol. 40(31)
Hong Kong Polytechnic University (HK), University of Alberta (CA)
Alberta Innovates, Natural Sciences and Engineering Research Council of Canada
Openalex Percentile: Top 57%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Time–cost combined optimization in planning infrastructure construction projects under environment induced time‐window constraints — Serhii Naumets, Ming Lu, et al. · Computer-Aided Civil and Infrastructure Engineering (2025) | TGRS Research Map | TGRS