Resource leveling with subcontracting: algorithms and complexity

Abstract A central problem in project management is the optimal use of limited resources. We consider the resource leveling problem, which minimizes the maximum resource load over the life of a project. This problem is motivated by the need to limit expensive resource acquisition. For several variants of this problem, we either provide an efficient optimal algorithm or show that the problem is intractable. We also consider a generalization of the resource leveling problem where work can be subcontracted. The subcontracting cost is defined either by task or by time of subcontracting. Our results show how the solvability of resource leveling problems depends on whether task times are unit or arbitrary, whether resource requirements are unit or binary, whether the project network is a chain, a tree, or an opposing forest, whether subcontracting costs for jobs are unit or binary, and whether the availability of subcontracting at a time period is constrained.

Authors

Institutions

Publication Details

Journal
Journal of Scheduling
Published
2025-12-01
DOI
https://doi.org/10.1007/s10951-025-00861-0
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Resource leveling with subcontracting: algorithms and complexity

Nicholas G. Hall, Marc E. Posner
Journal of Scheduling
Resource-Constrained Project Scheduling
article

Resource leveling with subcontracting: algorithms and complexity

Nicholas G. Hall, Marc E. Posner
article en

Abstract

Abstract A central problem in project management is the optimal use of limited resources. We consider the resource leveling problem, which minimizes the maximum resource load over the life of a project. This problem is motivated by the need to limit expensive resource acquisition. For several variants of this problem, we either provide an efficient optimal algorithm or show that the problem is intractable. We also consider a generalization of the resource leveling problem where work can be subcontracted. The subcontracting cost is defined either by task or by time of subcontracting. Our results show how the solvability of resource leveling problems depends on whether task times are unit or arbitrary, whether resource requirements are unit or binary, whether the project network is a chain, a tree, or an opposing forest, whether subcontracting costs for jobs are unit or binary, and whether the availability of subcontracting at a time period is constrained.

Journal of SchedulingVol. 29(1)
Fisher College (US), The Ohio State University (US)
Openalex Percentile: Top 57%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Resource leveling with subcontracting: algorithms and complexity — Nicholas G. Hall, Marc E. Posner · Journal of Scheduling (2025) | TGRS Research Map | TGRS