A new bi-objective model for resource-constrained project scheduling and cash flow problems with financial constraints under uncertainty: a case study

Owing to the importance of project cash flow, which comprises an entire history of all cash inflows and cash outflows, to economic survival of firms, it is vital to coping with project scheduling issues considering resource constraints in circumstances involving cash flow. Furthermore, since appropriate project management is subject to the innate uncertainties involved in most projects, they are required to be appraised respecting their profound impact. In this paper, a new comprehensive multi-mode multi-objective linear programming model with two conflicting objectives, which are maximizing final cash flow for profit optimization and shortening the duration of project execution, considering improving assumptions, that is, payments delays, project finance constraints, initial capital, different types of interest rates, credit limit to assuage financial distress, credit line usage, is presented in an uncertain environment. Since the model is considered as multi-objective with uncertain parameters, a new extended interval valued fuzzy - Torabi and Hassini (IVF-TH) approach is proposed to tackle the problem. The presented mixed integer linear programming (MILP) model is solved applying CPLEX solver. In addition, a real construction project in oil and gas industry is presented as a case study to illustrate the model applications. Ultimately, for the purpose of assessing the outcomes, a sensitivity analysis is implemented, and the performance of the proposed solution approach is compared to the previous multi-objective optimization methods using both case study and large problem instances.

Authors

Institutions

Publication Details

Journal
International Journal of Construction Management
Published
2026-05-22
DOI
https://doi.org/10.1080/15623599.2026.2669833
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A new bi-objective model for resource-constrained project scheduling and cash flow problems with financial constraints under uncertainty: a case study

Mohammad Ghasemi, Seyed-Ali Mirnezami, Reza Shahabi-Shahmiri
International Journal of Construction Management
Resource-Constrained Project Scheduling
article

A new bi-objective model for resource-constrained project scheduling and cash flow problems with financial constraints under uncertainty: a case study

Mohammad Ghasemi, Seyed-Ali Mirnezami, Reza Shahabi-Shahmiri
article en

Abstract

Owing to the importance of project cash flow, which comprises an entire history of all cash inflows and cash outflows, to economic survival of firms, it is vital to coping with project scheduling issues considering resource constraints in circumstances involving cash flow. Furthermore, since appropriate project management is subject to the innate uncertainties involved in most projects, they are required to be appraised respecting their profound impact. In this paper, a new comprehensive multi-mode multi-objective linear programming model with two conflicting objectives, which are maximizing final cash flow for profit optimization and shortening the duration of project execution, considering improving assumptions, that is, payments delays, project finance constraints, initial capital, different types of interest rates, credit limit to assuage financial distress, credit line usage, is presented in an uncertain environment. Since the model is considered as multi-objective with uncertain parameters, a new extended interval valued fuzzy - Torabi and Hassini (IVF-TH) approach is proposed to tackle the problem. The presented mixed integer linear programming (MILP) model is solved applying CPLEX solver. In addition, a real construction project in oil and gas industry is presented as a case study to illustrate the model applications. Ultimately, for the purpose of assessing the outcomes, a sensitivity analysis is implemented, and the performance of the proposed solution approach is compared to the previous multi-objective optimization methods using both case study and large problem instances.

International Journal of Construction Management
Shahed University (IR), Deakin University (AU), University of Tehran (IR)
Deakin University
Openalex Percentile: Top 99%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.